High-Level Timeline

...

(tick)

...

 September thru the end of October - Plan,

...

create/update test scripts in ALM, move pending support & project work into production.
(blue star) 10(tick) 10/12/2017 - SAP release of year end base level support pack

...

(tick) 10/

...

19/2017 - Last date to implement support & enhancement changes until freeze ends on 12/

...

13/2017

...

(tick) 10/

...

20/2017 - Development Freeze begins

...

(tick) 10/

...

23/2017 - End of day production snapshot to be used to refresh test environments (9/

...

25 for SF3)

...

(tick) 10/

...

25/2017 - Unit test

(info) 10(tick) 11/3002/2017 - 1011/3103/2017 Controlled Payroll Runs (SH2)

...

(tick) 11/

...

06/2017 - System Integration Test (regression test fixes: 11/

...

29-

...

30/2017)

(warning)(tick) 12/08/2017 - Go-live weekend! (start Friday at 5pm)

...