High-Level Timeline

...

Now and thru

...

October 25 - Plan, create/update test scripts in ALM. (SAP Business Areas)
(info) 10/10/2019 - SAP release of year end base level support pack (SAP)
End of day production snapshot from 9/30 to be used to refresh test environments

----------

Oct 7- Oct 10 - Validate automated test cases - complete
Oct 7 - take snapshot for SH2 refresh - complete
Oct 9 - Last transport meeting for

...

production support & enhancement changes until support pack work is complete - complete

...

(info) 10/10/2019 - Restricted Development Period begins
(info) 10/21/2019 - End of day production snapshot to be used to refresh test environments (9/30 for SF3)

Oct 10 - SAP release of year end base level support pack (SAP) - complete
Oct 16 5PM - SF2 restricted development mode starts - complete
Oct 17 - Nov 1: Automated Testing SF3 - complete
Oct 17 - Oct 18 - Unit test  SF3 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct 21 - Oct 25 - Unit test  SF2 - IS&T and EpiUse

...

Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP)

...

- complete
Oct 29- Oct 30 -  Controlled Payroll Run Test  - (IS&T HR and EpiUse Support Team) - Complete

...

Oct

...

29 - Nov

...

13- System Integration

...

Test  (Central Office Business Teams) - complete
Oct 29 - VPF test to compare year-to-date tax information with production - complete
Nov 14 - Nov 15 - Bug fixes and regression testing (Central Office Business Teams, IS&T and EpiUse)

...

- complete
Nov 18 - Nov 22 - Uptime Production Cut-over Activities - in progress

Nov 22 - Nov 24

...

- Go-live weekend! (start Friday at 5pm)

...

Nov 25 - Upgraded  PS1 is ready for use

---------

SAP Scheduled Upgrades - Ancillary Systems
ERP Target

 was: EHP8 for ERP 6.0 SPS 13 w/HR SP72 and HANA 2.0 SPS 03 Revision 037.01

 now: EHP8 for ERP 6.0 SPS 13 w/HR SP72 and HANA 2.0 SPS 03 Revision 037.02

 

ERP:

 SF3 Database Update: Thursday, September 26 2019 (Done)

 

GRC:

ACD Database Update: Wednesday, October 02 2019

 ACD Software Update: Monday, October 07 2019 -> Thursday, October 10 2019

 

NetWeaver/ADS:

DSD Database Update: Wednesday, October 02 2019

 DSD Software Update: Tuesday, October 08 2019 -> Friday, October 11 2019

 

SAP Mobile:

 SMD Database Update: Wednesday, October 02 2019