High-Level Timeline

...

(tick) Now

...

thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
(tick) 10/11/2012 – SAP release of year end base level support pack
(tick) 10/20-21/2012 – Production outage; DB & OS upgrade

...

Day

...

Start

...

End

...

Task

...

Area Responsible

...

10/20 Saturday

...

1:30am

...

7:00am

...

System Backups

...

OIS

...

10/20 Saturday

...

7:00am

...

11:00am

...

Oracle Upgrade

...

R3-Admin

...

10/20 Saturday

...

7:00am

...

10/21 Sunday 1:00am

...

Linux System Upgrade

...

OIS

...

10/21 Sunday

...

1:00am

...

8:00am

...

Post Linux Upgrade SAP Processing

...

R3-Admin

...

10/21 Sunday

...

8:00am

...

9:00am

...

Production Validation

...

Admin Systems, Tech Services

...

10/21 Sunday

...

9:00am

...

System Opened up to the MIT Community

...

R3-Admin

(tick) 10/22/2012 - End of day production snapshot to be used to refresh test environments
(tick) 10/22/2012 - Development Freeze begins
(tick) 11/01/2012 - Last date to implement support & enhancement changes until freeze ends on 12/5/2012
(tick) 10/26/2012 - 11/2/2012 Unit test

(tick) 11/5/2012 - 11/27/2012 System Integration Test

(green star) 12/1/2012 - 12/2/2012 Go-live weekend!

(tick) 12/5/2012 - Development Freeze ends