Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migration of unmigrated content due to installation of a new plugin

 

Result or Product of this Process

Round Rectangle
bgcolor #e6f2ff

This is an administrative process that results in a project being added to e-Builder. Aside from the start and energy project reviews, the entire process is largely automated.

Composition Setup
 

Process Details

Deck of Cards
idMOU
Card
labelSummary
  • This process starts when provides new project information is provided to the e-Builder administrator.
  • The primary actor for this process is the e-B admin.
  • The e-B administrator creates the project in e-Builder.
  • This process can be started by:
    • CC Planner
    • CC Planning Manager
    • CRSP Admin
    • CRSP Admin Assistant
    • OCP Director
    • OCP Planner
    • Program Manager
    • Project Manager
    • SEG Director
    • UTILITIES-Program Manager 
    The process does not spawn other processes.
Card
labelProcess Map

Image RemovedImage Added

Card
labelTraining: Actors and Actions

This process is limited to the eB admin. No user training is required. Refer any questions to the eB admin.

e-Builder Instructions

To complete this process the eB administrator must first receive all of the required information about the project once it has been approved

Step Descriptions

1 The requestor fills out the Project Initiation form, providing information about the project.

2 The information is approved for Energy projects by the Program Manager,

3 The e-B admin completes the process.

 The e-Builder admin enters all project information into the e-Builder form to complete the project set up.