Gerhard Kronschnabl and Alexander Neidhardt - 24 Feb 2016

HartRAO

Current status: The assembly of the main reflector is underway with the quadrupod and sub-reflector to be mounted in the next few weeks.The big lift is expected to happen around the week of the 12th of June. Panel alignment is underway (last results were around 90 microns).

Commissioning tests are to be started in the beginning of August.

We have a live camera feed up and running (updated every minute) which can be accessed at: http://www.hartrao.ac.za/xxvgs_liveview.php

Photos from HartRAO VGOS site (22 May 14 July 2017)

Image RemovedImage Removed

Image Removed

Image Added

Currently there is a camera installed on site, network access has been established to the site but not yet to the camera. For updated videos and photos please visit (I have unfortunately not had time to update these photos and videos recently though we are working towards getting a live stream feed operational within the next month - before the big lift):

HartRAO VGOS radio telescope

...

HartRAO Assembly Photos

Philip Mey - 24 May 21 July 2017

Ishioka

  1. Operation of Ishioka antenna is now under interruption because of construction of operation building, and will resume after April. 
  2. Modification of cryogenic dewar for QRFH system is being done. 

...