Gerhard Kronschnabl and Alexander Neidhardt - 24 Feb 2016

HartRAO

Current status: Big lift happened on the 19th and 20th of June without any problems. Leveling of azimuth cabin has been completed.Panel alignment is underway (last results were around 90 microns).

Commissioning tests are to be started in the beginning of AugustThere is still quite a lot of work to be done on the inside, but we are getting there.

We have a live camera feed up and running (updated every minute) which can be accessed at: http://www.hartrao.ac.za/xxvgs_liveview.php

Photos from HartRAO VGOS site (22 June 14 July 2017)

Image RemovedImage RemovedImage Added

For updated videos and photos please visit:

...

HartRAO Assembly Photos

Philip Mey - 22 June 21 July 2017

Ishioka

  1. Operation of Ishioka antenna is now under interruption because of construction of operation building, and will resume after April. 
  2. Modification of cryogenic dewar for QRFH system is being done. 

...