Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

Result or Product of this Process

Round Rectangle
bgcolor#e6f2ff

The purpose of the Project Definition Form Creation process is to create and route a PD Form through an approval system for non-Capital and non-Academic projects.  This process spawns the Team Assignment process.

Composition Setup
 

Process Details

Deck of Cards
idPD
Card
labelSummary
  • This process
can be started by
  • is usually initiated by the CC planner or the project manager. Other roles with the ability to being the process are:
    • CC
    PlannerCC
    • Planning
    Manager
  • eB Admin
  • Project
    • Manager
    • R&M Manager
    • UTLITIES-Program Manager
    • e-B Admin
  • When not started by the CC planner the process routes to the CC planner as the second step.
  • After the PD form is completed this process spawns the 03.01 Milestone Project Budget Estimate process.
Card
labelProcess Map

Image RemovedImage Added

Card
labelStep Descriptions

Toggle Cloak
1. Start

The process is started by any of the eligible roles. The process form is completed, when finished click Submit.
Cloak
  • If the process was initiated by CC Planner, the next step is Project Manager Review.
  • If not initiated by CC Planner, the next step is CC Planner Completes PD Form
Toggle Cloak
2
  • .
CC Planner Created? (Decision Step)
Cloak
  • If the initiator is the CC Planner the next step is Project Manager Review
  • If the initiator is not the CC Planner then the next step is CC Planner Completes PD Form

Toggle Cloak
3. CC Planner Completes PD Form

Cloak
  • CC Planner reviews the process, completes the required fields and has the option to selects one of the following actions: Submit, Revise or Void.
  • If Submit is chosen the next step is Project Manager ReviewIf Revise is chosen the next step is Initiator Review.
  • If Void is chosen the next step is Finish. The process is set to a Void status.

Toggle Cloak
 4. Project Manager Review

Cloak
  • The Project Manager reviews the process , completes the required fields and chooses to Submit or Revisewith the option to approve and Submit or to Revise.
  • To approve and submit the project manager must complete the required fields including section 9.1 on the process form by choosing the date.
  • If Submit is chosen the next step is Planning Manager and Prog. Manager Review.
  • If Revise is chosen the next step is CC Planner Revise
Toggle Cloak
5
  • .
Initiator Review
Cloak
  • The process Initiator reviews the process, completes the required fields and clicks Reply.
  • The next step is CC Planner Completes PD Form

Toggle Cloak
6. CC Planner Revise

Cloak
  • The CC Planner reviews the process, completes the required fields, and clicks Resubmit.
  • The next step is Project Manager Review.

Toggle Cloak
7. Planning Manager and Prog. Manager Review

Cloak
  • Project Manager and Program Manager review the process, complete the required fields and choose to Submit or Revise.
  • If Submit is chosen the next step is Working Committee Review
  • IfRevise is chosen the next step is CC Planner Revise

Toggle Cloak
Spawn 3.01a Budget Approval Process

Cloak
  • This step initiates a Budget Approval Process.
  • The project manager attaches the budget request spreadsheet requesting the Capital Renewal funding.
  • Upon the successful spawning of this Budget Approval Process the next step is Project Manager Review.

Toggle Cloak
Working Committee Review

Cloak

CC Planning Manager reviews the process with the working committee outside of e-Builder, completes the required fields and chooses one of these actions:

  1. Submit
    Next Step: Utilities, O&M and SEG Review
  2. Put On Hold
    Next Step: Finish

Toggle Cloak
Utilities, O&M and SEG Review

  • In this step the The working committee reviews the budget request
  • When Submit is chosen the next step is Property Office Review
  • If Put on Hold is chosen the next step is Finish.

Toggle Cloak
Property Office Review Step

Cloak
  • In this step the Property Office reviews the information that has been entered to the process. The Property office then indicates whether or not they agree with the funding type. If the Property Office disagrees with the funding type they should select the have made a change to the funding type on the PD option of the Property Office Review field.
  • When Submit is chosen the next step is M(ail) M(erge) Property Office.

Toggle Cloak
Mail Merge (Automation) Property Office

Cloak
  • This automation step sends an e-mail to the Property Office showing the information that has been entered into the process.
  • When this step completes successfully the next step is R&M, Utilities, FEG, CC Plnng Review.

Toggle Cloak
R&M, Utilities, FEG, CC Plnng Review

Cloak
  • In this step the CC Planner, Utilities Director, R
Cloak
Utilities Director, O
  • &M Director, and SEG Assignor
will
  • review the process, add their comments and click Submit.
Next Step: CC Director, Ops, and M&U Review
  • The next step is Create PD Form

Toggle Cloak
CC Director, Ops, and M&U Directr & VP, CSS Review

Cloak
  • In this step the information entered is reviewed by by the CC Director,
M&U Director and IBO Director will review the process, add their comments and click Submit.Next Step: CRSP Planning Review
  • and the VP, CSS Director.
  • When the Submit action is taken the next step is Create PD Form.

Toggle Cloak
DoF Planning Manager (Governance)

Cloak

CC Planning Manager reviews the process, adds comments, prepares the Capital Renewal List for the RCRSP agenda and clicks Submit:

Next Step: Spawn Team Assignment

Toggle Cloak
Spawn Team Assignments

Cloak

When a Submit action is taken from the DoF Planning Manager step, the process proceeds to this spawned step. In the spawn step the 2.01 - Team Assignment process starts and is moved to the first step of that workflow. The following action is automatically taken after:

Next Step: Finance Office Issues IO Number

Toggle Cloak
Finance Officer Issues IO Number

Cloak

Financial Officer reviews the process, adds the Cost Object Number, and clicks Submit.

Next Step: Apply Funding

Toggle Cloak
Apply Funding

Cloak

Financial Analyst reviews the process, applies funding, and clicks Submit:

Next Step: Finish

Finish

 

 

 

Create PD Form

Cloak
  • In this automation step e-Builder creates the the PD form and stores it in the Documents folder.

  • Upon successful completion of the PD form mail merge the next step is CC Planning Manager Hold - Record Approvals

Toggle Cloak
CC Planning Manager Hold - Record Approvals

Cloak
  • In this step, the approved Capital Renewal allocation is recorded.
  • When the Create Final PD action is taken the next step is Create Final PD Form.

Toggle Cloak
Create Final PD Form

Cloak
  • In this automation step e-Builder creates the Final PD form.
  • Upon successful completion of the Final PD form mail merge the next step is Finish.

Toggle Cloak
Finish

Cloak

...