Cutover plan

...


||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1319039659578|          |donovan@mit.edu|Send message to MIT-SAP community about upcoming SAP outage.  (message at end of plan)|
|F|M|F|1319054838799|          |donovan@mit.edu|*testing bld* gfsohjtoisht|
|T|M|F|          |1319055338375|donovan@mit.edu|*Wednesday, 11/23/2011 by 9AM (5 minutes)*. Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage|

...


||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|          |          |donovan@mit.edu|Update Firewall to restrict access to SAP gateway;send confirmation to R3-Admin when complete, cc fquern@mit.edu|

Go-live weekend 12/2-12/5.


Panel

Cut-over Plan Detail

Cut-over Plan Check List

...

Task #

...

Date

...

Time

...

Action / Task

...

Person(s)
Responsible

...

Status

...

 

...

 

...

Pre-Update Schedule and Processes

...

 

...

 

...

 

...

 

...

 

...

Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage.
(message can be found at end of this document)

...

 

...

 

...

 

...

 

...

 

...

 

...

 

...

 

 
Date
Time
Action / Task
Person(s)
Responsible
Status

...

Pre-Update Schedule and Processes

...

Thursday
12/2/10

...

√ By 9 AM
(5 Minutes)

...

Web-Tech
(JAD)

...

(tick)

...

Thursday
12/2/10

...

√ 12 PM

...

Send message to MIT-SAP community about upcoming SAP outage.
(message at end of this document)

...

Project Manager
(Frank Quern)

...

 

...

Thursday 12/2/10

...

√ 12 PM

...

Post message on SAPgui indicating upcoming SAP outage

...

R3-Admin
(R. Parker)

...

 

...

Friday
12/3/10

...

√ 11:00 AM

...

Cutover weekend planning meeting at SAPBiz-- NE49 Grand Cayman.

...

SAPBiz,
BPOs,
Admin Sys

...

 

...

Monday 12/6/2010

...

√ 12:00 PM

...

Steering Committee Meeting – review cut-over plan – NE49

...

Steering Committee

...

 

...

Wednesday
12/8/10

...

√ 6:30 AM

...

Switch ADS server pointing to production from J31 to J01.

...

R3-Admin
(R. Katkowski)

...

 

...

√ 10 AM- 12 PM
(noon)

...

SAP Upgrade Core/Action log team meeting to review the Production Cutover schedule and details, including action log and user support

...

Support Pack Action log Team,
Support Pack Core Team.

...

 

...

√ By 1 PM

...

Steering Committee, after final review of test results, Go/No-go decision

...

Steering Committee

...

 

...

√ 1 – 5 PM

...

SAP PI/ADS: Apply JSPM  Package/SPAM Package/SPS 7/SAP Kernel/Perform SGEN

...

R3-Admin
(R. Katkowski)

...

 

...

Thursday
12/9/10

...

√ 8 - 10 AM

...

SAP PI/ADS: Upgrade Oracle DB (Apply 10.2 patches/Install 11.2 software/Apply 11.2 patches)

...

R3-Admin
(R. Katkowski)

...

 

...

√ 10--11 AM

...

SAP PI/ADS: Convert Oracle Database

...

R3-Admin
(R. Katkowski)

...

 

...

Thursday
12/9/10

...

√ 9:00 AM

...

Email Steering Committee Go/No-go decision

...

Project Manager
( Frank Quern)

...

 

...

√ 2:00 – 3:00PM

...

Final review all issues in RT project queue, transport list, and web components.

...

R3-Admin /Core Team/ABAP Team/Web-Tech/BAs

...

 

...

√ By 4 PM

...

Schedule Pre & Post Trial Balance reports to be used by R3-Admin for controlled data comparisons.

...

VPF Finance
(B. Reeves)
Admin Systems
(B. Casey)

...

 

...

√ By 5 PM
(actual 11:30 PM)

...

R3-Admin email message
about system down time

...

R3-Admin
(R. Parker)

...

 

...

√ By 5 PM

...

Final Copy of the Production Update Schedule published and emailed.

...

Project Manager
(Frank Quern)

...

 

...

Friday
12/10/10

...

√ By 12 PM (noon)

...

Facility supervisors print out work lists as back up for Monday Morning

...

Facilities
(L. St. Croix)

...

 

...

√ By 12 PM (noon)
(3 Hours)

...

Reschedule (shift) DW batch jobs to Sunday night (10PM & 12AM).

...

DW 
(E. Zhitnikov)

...

 

...

√ By 4:30 PM

...

Suspend weekend MITSIS Grad Appointment Feed

...

Enterprise Appl. Admin
(K. Mullins)

...

 

...

√ By 5:45 PM

...

Workflow and JV Validation Reports

  • Workflow inbox report
  • JV Parked Documents Report

...

VPF
(Yan Jiang)

...

 

...

√ 5:35 PM
(5 Minutes)

...

Stop EDI Production Jobs (5 Minutes)

...

Tech Services
(E. Prudden)

...

 

...

√ 6 PM
(15 Minutes)

...

Shut down EDI application server (note: email sent to EDI partners earlier in the week notifying them of the shutdown window).

  • Run the push POs job
  • Shutdown the web server
  • Shutdown the application server

...

Enterprise Appl. Admin
(O. Wang)

...

 

...

√ 6 PM

...

Voice message update when system goes down (617-324-7468*)*

...

Project Manager
(F. Quern)

...

 

...

√ 6 PM

...

System Downtime Message (3 Down)

...

R3-Admin

...

 

...

√ 6 PM

...

Bring down application servers. Production Environment becomes unavailable to users (including SAPWeb, Self Service and ECAT).

...

R3-Admin

...

 

...

√ 6 PM
(5 Minutes)

...

Disable Gateways:
Enable “PS1 System Unavailable” redirect on SAPweb & Self Service/insideMIT web sites (including EHS specific message activating their manual reporting of injuries)

...

Web-Tech
(JAD)

...

 

...

√ 6 PM
(5 Minutes)

...

Suspend Drop-box processing.

...

Tech Services
(Wai-ming Li)

...

 

...

√ 6 PM
(30 Minutes)

...

OAS Upgrade Project intersection (switch over to OAS 10.1.3)

...

Web-Tech
(JAD)

...

 

...

√ 6 PM
(10 Minutes)

...

  1. htdocs/dhtml/js/map/map.url.js
  2. htdocs/dhtml/js/src/mit/insidemit.js

...

Web-Tech
(JAD)

...

 

...

√ 6 – 8 PM

...

Validation Reports (Trial Balance) executed in SAP.

  • Ron notifies Becky Reeves via email cc fquern@mit.edu, rcasey@mit.edu, mcnlee@mit.edu that the reports are complete & downloaded.
  • VPF confirms the receipt of the Trial Balance Report.

...

 

...

√ 6 – 8 PM

...

Limited activity in PS1.

  • With the exception of the Data warehouse jobs (and the trial balances) shift the remaining time-scheduled non-infrastructure jobs to execute after the weekend cutover activities (after 6am on Monday
  • Users locked
  • Save WT info to internal SAP table

...

R3-Admin
(R. Parker)
(G. Petrowsky)

...

 

...

Support Pack Application and Processes

...

X 6 – 7 PM

...

R3-Admin
]]></ac:plain-text-body></ac:structured-macro>
(R. Parker)
Enterprise System Admin.
(N. Thaler)

...

 

...

√ 6 - 8 PM

...

SAP Portal: Upgrade Oracle DB (Apply 10.2 patches/Install 11.2 software/Apply 11.2 patches)

...

R3-Admin
(D. Nugent)

...

 

...

√ 8 – 9 PM

...

SAP Portal: Convert Oracle Database

...

R3-Admin
(D. Nugent)

...

 

...

√ 8 – 11PM

...

Backup PS1.

  • Bring down the SAP systems
  • Perform split mirror back-up

...

R3-Admin
(R. Parker)
Enterprise Storage & Backup
(D. Romnes)

...

 

...

Friday
12/10/10 – Saturday 12/11/10

...

√ 11 PM
-
12 PM
(noon)

...

SAP ERP: Execute support pack application (see detail cut-over project plan found on wiki in cutover section)

  • Email Notification to sap-upgrade-core@mit.edu from Ron Parker at the start of the support pack application
  • Email notifications to sap-upgrade-core@mit.edu by 12:00 midnight on Friday (12/10) and by 12:00 noon on Saturday (12/11) from Ron Parker.

...

R3-Admin

...

 

...

Saturday
12/11/2010

...

√ 12 PM --
2 PM

...

SAP Portal: Apply JSPM Package/SPS 7/SAP Kernel

...

R3-Admin
(D. Nugent)

...

 

...

 

...

√ 1 – 5 PM

...

Backup System (R-MAN)

...

R3-Admin
OIS

...

 

...

√ By 3 PM

...

Upgraded GuiXT scripts moved to Facilities Production Server

...

Facilities
(M. Sherman)

...

 

...

 

...

√ 4 PM

...

Conference Call Check-in
Core Team Check in at 4pm on Saturday (12/11/10) (use conference call 617-324-7520 line)

...

Project Manager
(Frank Quern)
Project Sponsor
(Bart Dahlstrom)
Core Team

...

 

...

 

...

√ 5 – 10 PM

...

Execute Oracle DB Upgrade (see detail cut-over project plan found on wiki in cutover section)

...

R3-Admin

...

 

...

 

...

√10 PM – 2 AM (Sunday)

...

Backup System (R-MAN)

...

R3-Admin
(R. Parker)
Enterprise Storage & Backup
(P. Whitney)

...

 

...

√ 10 PM -  1 AM (Sunday)
(2.5 Hours)

...

Generate DB Statistics
Complete ABAP Loads

...

R3-Admin

...

 

...

Sunday 12/12/10 (morning)

...

√ 1 – 3 AM

Transports Application (see detail cut-over project plan found on wiki in cutover section)

...

R3-Admin

...

 

...

Post Upgrade Schedule and Processes

...

Sunday
12/12/10

...

√  8 AM

...

Validation reports executed (trial balance reports)

  • R3-ADMIN notifies Becky Reeves via email with a copy to Frank Quern as soon as the trial balance is available for review
  • R3-ADMIN unlock BREEVES id in PS1
  • Becky notifies Frank Quern when validation of the trial balance report is complete.

...

R3-Admin
(R. Parker)
VPF Finance
(B. Reeves)

...

 

...

√ 10 AM

...

Unlock web-services ids in Production
JAD (Jim Dobrovic)
SML (Steve Landry)
SSELIGMA (Seth Seligman)
BKNOLL (Brian Knoll)

...

R3-Admin
(G. Petrowsky)

...

 

...

√ 10 - 11 AM
(1 Hour)

...

OAS Upgrade Project intersection (verify new OAS 10.1.3 is operational)

...

Web Services
(JAD)
(SML)
(SSELIGMA)
(BKNOLL)

...

 

...

√  By  11 AM
(5 Minutes)

...

Enable Gateways (SAPWeb/ESS)

...

Web-tech
(JAD)

...

 

...

√  By 11 AM
(5 Minutes)

...

Schedule EDI Job

  • Unlock ids
  • Schedule EDI Job
    <ac:structured-macro ac:name="unmigrated-wiki-markup" ac:schema-version="1" ac:macro-id="eb30d2f3-23ee-4045-9542-f45952011173"><ac:plain-text-body><![CDATA[* Monitor first job released (on the ½ hr)[perform this task after task 50]

...

R3-Admin
]]></ac:plain-text-body></ac:structured-macro>
(G. Petrowski)
Tech Services
(E. Prudden)
(ZZLOGISBAT01)

...

 

...

√ By 11 AM

...

Turn on the EDI “gourmet-1” server
<ac:structured-macro ac:name="unmigrated-wiki-markup" ac:schema-version="1" ac:macro-id="0911eca0-22ed-480c-be15-d8fc0d760718"><ac:plain-text-body><![CDATA[[perform this task before task 49]

...

Enterprise Appl. Admin
]]></ac:plain-text-body></ac:structured-macro>
(Olivia Wang)

...

 

...

√ By 11 AM

...

Email to ist-sap@mit.edu

...

√  By 11 AM

...

Switch ADS server connection back from J01 to J31 (updated version)

...

R3-Admin
(R. Katkowski)

...

 

...

√  11 AM
(1 Hour)

...

R3-Admin Action Log

...

R3-Admin
(All)

...

 

...

√ 12 PM --
2 PM

...

  • ADMIN SYS Action Log users unlocked

...

√ By 2 PM

...

Update voice message whether Data Validation is on schedule.
Email to SAP-Validation-team@mit.edu that the validation is to start on schedule

...

Project Manager
(Frank Quern)

...

 

...

√ By 2 PM

...

Unlock testers

...

R3-Admin

...

 

...

√ 2 PM --
4 PM

...

PS1 Data Validations & Transaction processing listed in section 3 below performed by designated users;
SAPWeb and Self Service will be available for validation;
All servers will be available.

...

BPOs 
Admin Sys BAs

...

 

...

√ By 4 PM

...

Coordinators for each area should send email to sap-validation-team@mit.edu at the completion of the validation notifying results

...

BPOs 
Admin Sys BAs
R3-Admin

...

 

...

√ 4 PM

...

Conference Call Check-in
Go/No Go conference call 617-324-7520 (Process owners, B. Dahlstrom, R. Parker, K. Lyons, Admin Sys Team Leads)

...

Business Owners/
Test Coordinators
Sponsor
(B. Dahlstrom)
Tech Services
(Kevin Lyons)
Admin Sys  Team Leads
IS&T Test Coordinators
(K. Le Vie),
(M. Donovan)

...

 

...

√ After con call

...

Send e-mail to (sapbiz, sap-upgrade-core, ist-sap@mit.edu,warehouse@mit.edu, Elena@mit.edu,) notifying results.

...

Project Manager
(Frank Quern)

...

 

...

8PM – 12AM

...

Data Warehouse Job Validation

...

√ 8PM – 10PM

...

Unlock users (Facilities, SMART)
Unlock all users
(R3-Admin notifies operations center at 3-1500).
At end of unlock send message to web-tech@mit.edu, with a copy to ist-sap@mit.edu, update gateway messages.

...

R3-Admin

...

 

...

√ 10 PM
Sunday
(5 Minutes)

...

Enable Drop box

...

Tech Services
(Wai-ming Li)

...

 

...

√ 10 PM

...

Execute ProCard from Bank of America Feed

...

Tech Services
(Eping Wei)

...

 

...

Monday
12/13/10

...

√ 1:30 AM

...

On Line back up of PS1

...

R3-Admin
(R. Parker)
Enterprise Storage & Backup
(P. Whitney)

...

 

...

√ By 6 AM

...

Update the 3-down web page & SAPgui message.

...

R3-Admin
(R. Parker)
Project Manager
(Frank Quern)

...

 

...

√ By 6 AM

...

Remove SAPweb, ESS and EHS messages

...

Web Services
(JAD)

...

 

...

6 AM

...

Email notification to the MIT Community stating the update is completed and Production is available.

...

Project Manager
(Frank Quern)

...

 

...

√ 9 AM

...

Reinstate weekend MITSIS Grad Appointment Feed

...

Enterprise Appl. Admin
(K. Mullins)

...