End of day production snapshot from 9/30 to be used to refresh test environments
----------
Oct 7- Oct 10
...
- Validate automated test cases - complete
Oct 7 - take snapshot for SH2 refresh - complete
Oct 9 - Last transport meeting for production support & enhancement changes until support pack work is complete
...
- complete
Oct 10 - SAP release of year end base level support pack (SAP) - complete
Oct 16 5PM - SF2 restricted development mode starts - complete
Oct 17 - Nov 1: Automated Testing SF3 - complete
Oct 17 - Oct 18 - Unit test SF3 - IS&T and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct 21 - Oct 25 - Unit
...
test SF2 - IS&T
...
and EpiUse Support Teams (Facilities, Finance, HR, R3, Release Engineering, SAP ABAP) - complete
Oct
...
29- Oct
...
30 - Controlled Payroll Run Test - (IS&T HR and EpiUse Support Team) - Complete
Oct
...
29 - Nov
...
13- System Integration Test (Central Office Business Teams) - complete
...
Oct 29 - VPF test to compare year-to-date tax information with production - complete
Nov 14 - Nov 15 - Bug fixes and regression testing (Central Office Business Teams
...
, IS&T and EpiUse) - complete
Nov
...
18 - Nov
...
22 - Uptime Production
...
Cut-over Activities - in progress
Nov
...
22 - Nov
...
24 - Go-live weekend! (start Friday at 5pm)
Nov
...
25 - Upgraded PS1 is ready for use
---------
SAP Scheduled Upgrades - Ancillary Systems
ERP Target
was: EHP8 for ERP 6.0 SPS 13 w/HR SP72 and HANA 2.0 SPS 03 Revision 037.01
now: EHP8 for ERP 6.0 SPS 13 w/HR SP72 and HANA 2.0 SPS 03 Revision 037.02
ERP:
SF3 Database Update: Thursday, September 26 2019 (Done)
GRC:
ACD Database Update: Wednesday, October 02 2019
ACD Software Update: Monday, October 07 2019 -> Thursday, October 10 2019
NetWeaver/ADS:
DSD Database Update: Wednesday, October 02 2019
DSD Software Update: Tuesday, October 08 2019 -> Friday, October 11 2019
SAP Mobile:
SMD Database Update: Wednesday, October 02 2019