Note:
...
Go-live weekend 12/2-12/5.
Cutover plan - Work in progress - tasks and dates NOT finalized.
| Tasklist |
|---|
Pre-Update Schedule and Processes | Pre-Update Schedule and Processes | | width | 80% |
|---|
||Completed||Priority||Locked||CreatedDate||CompletedDate||Assignee||Name||
|F|M|F|1319222115555| |donovan@mit.edu|*Tuesday, 11/22/2011, by 9 AM* Post messages on SAPweb and ESS Web sites of upcoming SAP outage.|
|F|M|F|1319222167545| |donovan@mit.edu|*Tuesday 11/22/2011, 12 PM* Send message to MIT-SAP community about upcoming SAP outage.|
|F|M|F|1319222216395| |donovan@mit.edu|*Tuesday, 11/22/2011, 12 PM* Post message on SAPgui indicating upcoming SAP outage.|
|F|M|F|1319222262777| |donovan@mit.edu|*Wednesday, 11/23/2011, 11:00 AM* SAPBiz - Cutover weekend planning meeting|
|F|M|F|1319222316994| |donovan@mit.edu|*Monday, 11/28/2011. 12 PM* Steering Committee Meeting - review cutover plan|
|F|M|F|1319222399230| |donovan@mit.edu|*Wednesday, 11/30/2011, 6:30AM* Switch ADS server pointing to production for J31 to J01|
|F|M|F|1319222474613| |donovan@mit.edu|*Wednesday, 11/30/2011, 10 AM-Noon* SAP upgrade Core/Action log team meeting - review Cutover schedule and details|
|F|M|F|1319222530271| |donovan@mit.edu|*Wednesday, 11/30/2011, 1:00 PM* Steering Committee, review test result, Go/No-Go decision|
|
| Tasklist |
|---|
| width | 80% |
|---|
| title | Support Pack Application and Processes |
|---|
|
| Tasklist |
|---|
|
| width | 80% |
|---|
title | Post Upgrade Schedule and Processes
|