GGAO and Westford resumed their VGOS Demonstration Series sessions in November and have observed three more sessions of 1, 5, and 24 hours.

Arthur Niell - 2016 Jan 27

Kokee

        The 12m signal chain installation / checkout is on schedule.

        1) All of the signal chain systems (frontend and backend) were installed by 1/21
        2) Frontend / Backend Integration completed 1/25
        3) Have begun signal chain integration testing and verification (estimated completion 2/5)

...