Yoshihiro Fukizaki - 28 Jan 2016

Onsala

First telescope currently being delivered. Two receiver systems under construction (QRFH and Eleven). First light date not defined, but hopefully this year.

...

– the first two containers from MTM with electronic equipment etc. are expected to arrive tomorrow, May 27
– six containers with reflector panels of the first telescope, etc. are expected to arrive around June 1st
– the az- and el-cabin of the first telescope are expected to arrive around June 8
– the assembling work will start immediately after that
– the containers for the second telescope are expected to arrive 1-2 weeks later
– the receiver design and development work for both telescopes is ongoing
– the 11-feed for system-1 is on site
– we are waiting on the CalTech QRFH for system-2
– the DBBC3s for both systems are ordered and expected to be delivered in October

Rüdiger Haas - 26 May 2016

Construction sites webcams.

...