You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 82 Next »

Result or Product of this Process

The purpose of the Project Definition Form Creation process is to create and route a PD Form through an approval system for non-Capital and non-Academic projects.  This process spawns the Team Assignment process.

Process Details

    This process can be started by:

    • CC Planner
    • CC Planning Manager
    • eB Admin
    • Project Manager
    • R&M Manager
    • UTLITIES-Program Manager

    1. Start

    2. CC Planner Created? (Decision Step)

    3. CC Planner Completes PD Form

     4. Project Manager Review

    5. Initiator Review

    6. CC Planner Revise

    7. Planning Manager and Prog. Manager Review

    8. Working Committee Review

    9. Utilities, O&M and SEG Review

    10. Create PD Form (Mail Merge Step)

    11. One Funding Source? (Conditional)

    12. Spawn 03.01 Milestone Project Estimate and Budget Request - (COST) (MPEB)

    13. Finish

     

     

     

     

    • No labels