Why is This Useful?

This report allows project managers to quickly find all information on imported general invoices from SAP from the previous day. The report includes the fields:

  • Project Name
  • Project Number
  • Project Status
  • Project Manager
  • Company Name
  • Invoice Description
  • Invoice Amount
  • SAP Invoice Number
  • Date Received
  • Date Paid

This report is filtered to include only invoices paid the previous day that do not have a commitment number on projects where the field e-Builder Only? = Yes.

Components

This report shows General Invoices from the previous day that are imported to e-Builder as actual costs.


    1. Time sheet charges, calculated as # of Hours * Billing rate for each workday. So if person xyz worked on Monday 5/4 and Wednesday 5/6, the charges will be listed as date received 5/4 and 5/6. Date paid is when the timesheet was entered into SAP. So if person xyz submitted their timesheet on 5/25, and it was entered on SAP on 5/28, the date paid will be 5/28, and that is when the charge will occur in eBuilder. That was a long way of asking you to submit timesheets promptly.

    2. Invoices against a PO that originated on SAP. If your PO was created a while ago, it might have been created directly on SAP. Any invoice against that PO will be imported into eB as a general invoice. eB always shows the actual cost, but will not be able to show the remaining PO balance, since the PO originated on SAP. 

    3. R&M charges from work orders, shut downs, etc. Will appear on budget code C50-685 Other MIT Internal Charges. These charges comes into eBuilder at the end of the month when SAP settlement routines run.

    4. Accounting JV’s where costs were moved between GL lines or between projects.

 Type of ChargeDefinition
ATime sheet chargesThis is calculated by taking the # of Hours x Billing rate for each workday.
BInvoices against a PO that originated on SAPAny invoice against that PO will be imported into eB as a general invoice from SAP.
CR&M chargesThese are charges from work orders, shut downs, etc.
DAccounting JV’sThese are costs that have moved between GL lines or between projects.

*The cost module shows the actual charges for your project, and can be broken into two simple types.

Sample Image