The following is a copy of the Support Pack Cut-over and Test Plans:

2021 SAP Support Pack Cutover Plan

2021 FLE Validations

2021 HRP Validations

2021 PS1 User List

2021 Final Post Upgrade Transport List

Communication

Project cut-over status of the upgrade, see below,  will be posted on this wiki page beginning at noon on Friday 12/4/2020 through noon on Monday 12/7/2020.  The Project Manager will update this message as needed.  A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.

Project Status: 
Tuesday September 21: Support Pack planning activities in progress

Conference Calls (Zoom) for cut-over weekend:

  • Saturday 4:30PM IS&T 
  • Sunday 1PM Validation review