The following is a copy of the Support Pack Cut-over and Test Plans:
2022 SAP Support Pack Cutover Plan
2022 FLE Validations
2022 HRP Validations
2022 PS1 User List
2021 Final Post Upgrade Transport List - to be updated by Elda
Communication
Project cutover status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/2/2022 through noon on Monday 12/5/2022. The Project Manager will update this message as needed. A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
Project Status:
Tue 11/29/22 9:00AM: Final cutover preparations are being performed. On track for Production update 5pm Friday (12/2) to 6am Monday (12/5)
|
|---|
Conference Calls (Zoom) for cut-over weekend:
Saturday 4:30PM IS&T
Sunday 1PM Validation review