This folder contains current copies of relevant project schedules. These schedules are attached in MSProject format an presented in HTML format.
High Level Plan for SAPBiz 10-8-08 v4
Project Start Date: Sat 9/20/08
Project Finish Date: Tue 12/23/08
ID |
Task_Name |
Duration |
Start_Date |
Finish_Date |
Predecessors |
Resource_Names |
|---|---|---|---|---|---|---|
1 |
2008 Support Pack Implementation Project |
65 days |
Mon 9/22/08 |
Tue 12/23/08 |
|
|
2 |
Project Prep |
33 days |
Mon 9/22/08 |
Thu 11/6/08 |
|
|
3 |
PS1 Snapshot at end of day |
0 days |
Mon 9/22/08 |
Mon 9/22/08 |
|
|
4 |
Transaction list available |
0 days |
Fri 9/26/08 |
Fri 9/26/08 |
|
R3 |
5 |
Identify test scenarios / transactions |
5 days |
Mon 9/29/08 |
Fri 10/3/08 |
4 |
BUS,BA |
6 |
Review and update test scripts |
20 days |
Mon 10/6/08 |
Fri 10/31/08 |
5 |
BUS,BA |
7 |
SF3 Unavailable at end of day |
0 days |
Fri 10/10/08 |
Fri 10/10/08 |
|
|
8 |
PS1 snapshot at end of day |
0 days |
Mon 10/20/08 |
Mon 10/20/08 |
|
R3 |
9 |
Execute Trial balance for snapshot |
0.5 days |
Mon 10/20/08 |
Mon 10/20/08 |
8 |
BUS |
10 |
Save data warehouse extracts |
0 days |
Fri 10/10/08 |
Fri 10/10/08 |
7 |
DWH |
11 |
Support packs available from SAP |
0 days |
Mon 10/20/08 |
Mon 10/20/08 |
|
|
12 |
PS1 Import 1 |
0 days |
Thu 10/23/08 |
Thu 10/23/08 |
|
|
13 |
PS1 Import 2 |
0 days |
Thu 10/30/08 |
Thu 10/30/08 |
|
|
14 |
PS1 Import 3 |
0 days |
Thu 11/6/08 |
Thu 11/6/08 |
|
|
15 |
SF3 System Refresh |
5 days |
Tue 10/14/08 |
Mon 10/20/08 |
|
|
16 |
Refresh with 9/22/08 PS1 Snapshot |
2 days |
Tue 10/14/08 |
Wed 10/15/08 |
|
R3 |
17 |
R3 Action Log |
0.5 days |
Thu 10/16/08 |
Thu 10/16/08 |
16 |
R3 |
18 |
Scramble sensitive data |
2.5 days |
Thu 10/16/08 |
Mon 10/20/08 |
17 |
R3 |
19 |
PS1 Snapshot at end of day |
0 days |
Mon 10/20/08 |
Mon 10/20/08 |
|
|
20 |
Execute Trial Balance for later comparison |
0.5 days |
Mon 10/20/08 |
Mon 10/20/08 |
19 |
R3 |
21 |
Support Packs available from SAP |
0 days |
Mon 10/20/08 |
Mon 10/20/08 |
|
|
22 |
SFK Update |
4 days |
Tue 10/21/08 |
Fri 10/24/08 |
|
|
23 |
Import Updates |
1 day |
Tue 10/21/08 |
Tue 10/21/08 |
21FS+1 day |
R3 |
24 |
Identify and resolve import issues |
1 day |
Wed 10/22/08 |
Wed 10/22/08 |
23 |
R3 |
25 |
Validate security infrastructure (SNC) |
1 day |
Thu 10/23/08 |
Thu 10/23/08 |
24 |
R3 |
26 |
Validate SAPGui interactions |
0.5 days |
Fri 10/24/08 |
Fri 10/24/08 |
25 |
R3 |
27 |
Validate basic SAP functions work |
0.5 days |
Fri 10/24/08 |
Fri 10/24/08 |
26 |
R3 |
28 |
SF3 Update |
5 days |
Mon 10/27/08 |
Fri 10/31/08 |
|
|
29 |
Import Updates |
2 days |
Mon 10/27/08 |
Tue 10/28/08 |
21,27 |
R3 |
30 |
Execute action log |
0.5 days |
Wed 10/29/08 |
Wed 10/29/08 |
29 |
DEV,BA |
31 |
Update action log as necessary |
0.5 days |
Wed 10/29/08 |
Wed 10/29/08 |
|
DEV,BA |
32 |
Produce collision report |
0.5 days |
Wed 10/29/08 |
Wed 10/29/08 |
29 |
R3 |
33 |
Review collision report |
1 day |
Wed 10/29/08 |
Thu 10/30/08 |
32 |
DEV,BA |
34 |
Reimplement MIT mods |
1 day |
Thu 10/30/08 |
Fri 10/31/08 |
33 |
DEV |
35 |
Confirm configuration steps work |
0.5 days |
Fri 10/31/08 |
Fri 10/31/08 |
34 |
DEV,BA |
36 |
Unit Test Preparation and Execution |
6 days |
Mon 11/3/08 |
Mon 11/10/08 |
|
|
37 |
Apply support packs to SF2 |
2 days |
Mon 11/3/08 |
Tue 11/4/08 |
35 |
R3 |
38 |
Update and Execute action log |
0.5 days |
Wed 11/5/08 |
Wed 11/5/08 |
37 |
BA,DEV |
39 |
Import transports from SF3 |
0.5 days |
Wed 11/5/08 |
Wed 11/5/08 |
38 |
R3 |
40 |
Unit test, resolution and retest in SF2 |
3 days |
Thu 11/6/08 |
Mon 11/10/08 |
39 |
BA,DEV |
41 |
System Test / User Acceptance Test Environment Preparations |
10 days |
Mon 10/27/08 |
Fri 11/7/08 |
|
|
42 |
Refresh TST with 10/20 snapshot, NO SCRAMBLING DATA |
3 days |
Mon 10/27/08 |
Wed 10/29/08 |
|
R3 |
43 |
Import post snapshot production transports (delta from 10/20 to 10/30) |
2 days |
Thu 10/30/08 |
Fri 10/31/08 |
42 |
R3 |
44 |
Import updates |
2 days |
Mon 11/3/08 |
Tue 11/4/08 |
43 |
R3 |
45 |
Import SF3 transports & post-update DEV transports (to be tested during SI & UAT) |
1 day |
Wed 11/5/08 |
Wed 11/5/08 |
44 |
DEV |
46 |
Execute trial balance and compare with TB from 10/20 |
0.5 days |
Thu 11/6/08 |
Thu 11/6/08 |
44,45 |
BUS |
47 |
Execute action log |
0.5 days |
Thu 11/6/08 |
Thu 11/6/08 |
46 |
DEV,BA |
48 |
Execute DWH extracts and comparison |
1 day |
Fri 11/7/08 |
Fri 11/7/08 |
47 |
DWH |
49 |
Development slowdown starts |
0 days |
Fri 11/7/08 |
Fri 11/7/08 |
48 |
|
50 |
Execute System Integration Tests |
6 days |
Wed 11/12/08 |
Wed 11/19/08 |
|
|
51 |
HR-Payroll |
6 days |
Wed 11/12/08 |
Wed 11/19/08 |
47,40 |
DEV,BA |
52 |
Logistics |
6 days |
Wed 11/12/08 |
Wed 11/19/08 |
47,40 |
DEV,BA |
53 |
EHS |
6 days |
Wed 11/12/08 |
Wed 11/19/08 |
47,40 |
DEV,BA |
54 |
Financial |
6 days |
Wed 11/12/08 |
Wed 11/19/08 |
47,40 |
DEV,BA |
55 |
Execute User Acceptance Test (UAT) |
15 days |
Thu 11/20/08 |
Fri 12/12/08 |
|
|
56 |
Payroll comparison (tasks and duration to be validated) |
3 days |
Thu 11/20/08 |
Mon 11/24/08 |
54 |
BA,BUS |
57 |
Execute UAT |
7 days |
Tue 11/25/08 |
Fri 12/5/08 |
56 |
BUS |
58 |
Financial Close |
1 day |
Mon 12/8/08 |
Mon 12/8/08 |
57 |
BUS |
59 |
Issue retesting |
2 days |
Tue 12/9/08 |
Wed 12/10/08 |
58 |
ALL |
60 |
Execute another financial close? |
1 day |
Thu 12/11/08 |
Thu 12/11/08 |
59 |
BUS |
61 |
UAT sign off |
1 day |
Fri 12/12/08 |
Fri 12/12/08 |
60 |
ALL |
62 |
Cutover weekend & Controlled Start |
2 days |
Sat 12/13/08 |
Sun 12/14/08 |
61 |
ALL |
63 |
Drop Dead Date for support packs in production |
0 days |
Mon 12/22/08 |
Mon 12/22/08 |
|
|
64 |
First Calendar 2009 Payroll |
0 days |
Tue 12/23/08 |
Tue 12/23/08 |
|
|