Important Dates
11/20 to 12/10 - User acceptance testing
- All testing done by 12/5
- 12/8 - 12/10 for issue retesting and financial closing
- Don't wait until the end to test
12/12 - Go / No Go Decision
- Based on results of user acceptance testing
- Business owners will indicate their approval and acceptance of testing
12/13 to 12/15 - Go live weekend
- Production will be down from 6pm Friday evening until 6am Monday morning
12/22 - Drop dead date for updating production with support packages
- We have to be done by this date
12/23 - first 2009 payroll run