Note: For cutover plan - Benefits needs to have the DW Benefits extracts extracted for Friday, Dec 2, before the shutdown. These files then need to be loaded into DW so Benefits can validate OE data during the weekend before data is sent to the vendors.
test bold
Test underline
test italics
test color red
Task # |
Date |
Time |
Action / Task |
Person(s) |
Status |
|---|---|---|---|---|---|
|
|
|
Pre-Update Schedule and Processes |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Date
Time
Action / Task
Person(s)
Responsible
Status
Pre-Update Schedule and Processes |
|||||
Thursday |
√ By 9 AM |
Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage. |
Web-Tech |
|
|
Thursday |
√ 12 PM |
Send message to MIT-SAP community about upcoming SAP outage. |
Project Manager |
|
|
Thursday 12/2/10 |
√ 12 PM |
Post message on SAPgui indicating upcoming SAP outage |
R3-Admin |
|
|
Friday |
√ 11:00 AM |
Cutover weekend planning meeting at SAPBiz-- NE49 Grand Cayman. |
SAPBiz, |
|
|
Monday 12/6/2010 |
√ 12:00 PM |
Steering Committee Meeting – review cut-over plan – NE49 |
Steering Committee |
|
|
Wednesday |
√ 6:30 AM |
Switch ADS server pointing to production from J31 to J01. |
R3-Admin |
|
|
|
√ 10 AM- 12 PM |
SAP Upgrade Core/Action log team meeting to review the Production Cutover schedule and details, including action log and user support |
Support Pack Action log Team, |
|
|
|
√ By 1 PM |
Steering Committee, after final review of test results, Go/No-go decision |
Steering Committee |
|
|
|
√ 1 – 5 PM |
SAP PI/ADS: Apply JSPM Package/SPAM Package/SPS 7/SAP Kernel/Perform SGEN |
R3-Admin |
|
|
Thursday |
√ 8 - 10 AM |
SAP PI/ADS: Upgrade Oracle DB (Apply 10.2 patches/Install 11.2 software/Apply 11.2 patches) |
R3-Admin |
|
|
|
√ 10--11 AM |
SAP PI/ADS: Convert Oracle Database |
R3-Admin |
|
|
Thursday |
√ 9:00 AM |
Email Steering Committee Go/No-go decision |
Project Manager |
|
|
√ 2:00 – 3:00PM |
Final review all issues in RT project queue, transport list, and web components. |
R3-Admin /Core Team/ABAP Team/Web-Tech/BAs |
|
||
√ By 4 PM |
Schedule Pre & Post Trial Balance reports to be used by R3-Admin for controlled data comparisons. |
VPF Finance |
|
||
√ By 5 PM |
R3-Admin email message |
R3-Admin |
|
||
√ By 5 PM |
Final Copy of the Production Update Schedule published and emailed. |
Project Manager |
|
||
Friday |
√ By 12 PM (noon) |
Facility supervisors print out work lists as back up for Monday Morning |
Facilities |
|
|
√ By 12 PM (noon) |
Reschedule (shift) DW batch jobs to Sunday night (10PM & 12AM). |
DW |
|
||
√ By 4:30 PM |
Suspend weekend MITSIS Grad Appointment Feed |
Enterprise Appl. Admin |
|
||
|
√ By 5:45 PM |
Workflow and JV Validation Reports
|
VPF |
|
|
|
√ 5:35 PM |
Stop EDI Production Jobs (5 Minutes) |
Tech Services |
|
|
|
√ 6 PM |
Shut down EDI application server (note: email sent to EDI partners earlier in the week notifying them of the shutdown window).
|
Enterprise Appl. Admin |
|
|
|
√ 6 PM |
Voice message update when system goes down (617-324-7468*)* |
Project Manager |
|
|
|
√ 6 PM |
System Downtime Message (3 Down) |
R3-Admin |
|
|
|
√ 6 PM |
Bring down application servers. Production Environment becomes unavailable to users (including SAPWeb, Self Service and ECAT). |
R3-Admin |
|
|
√ 6 PM |
Disable Gateways: |
Web-Tech |
|
||
|
√ 6 PM |
Suspend Drop-box processing. |
Tech Services |
|
|
|
√ 6 PM |
OAS Upgrade Project intersection (switch over to OAS 10.1.3) |
Web-Tech |
|
|
|
√ 6 PM |
Deploy apr_supplements web application
|
Web-Tech |
|
|
|
√ 6 – 8 PM |
Validation Reports (Trial Balance) executed in SAP.
|
R3-Admin |
|
|
√ 6 – 8 PM |
Limited activity in PS1.
|
R3-Admin |
|
||
Support Pack Application and Processes |
|||||
|
X 6 – 7 PM |
Update Firewall to restrict access to SAP gateway; send confirmation to R3-Admin when complete, cc fquern@mit.edu |
R3-Admin |
|
|
|
√ 6 - 8 PM |
SAP Portal: Upgrade Oracle DB (Apply 10.2 patches/Install 11.2 software/Apply 11.2 patches) |
R3-Admin |
|
|
√ 8 – 9 PM |
SAP Portal: Convert Oracle Database |
R3-Admin |
|
||
|
√ 8 – 11PM |
Backup PS1.
|
R3-Admin |
|
|
Friday |
√ 11 PM |
SAP ERP: Execute support pack application (see detail cut-over project plan found on wiki in cutover section)
|
R3-Admin |
|
|
Saturday |
√ 12 PM -- |
SAP Portal: Apply JSPM Package/SPS 7/SAP Kernel |
R3-Admin |
|
|
|
√ 1 – 5 PM |
Backup System (R-MAN) |
R3-Admin |
|
|
|
√ By 3 PM |
Upgraded GuiXT scripts moved to Facilities Production Server |
Facilities |
|
|
|
√ 4 PM |
Conference Call Check-in |
Project Manager |
|
|
|
√ 5 – 10 PM |
Execute Oracle DB Upgrade (see detail cut-over project plan found on wiki in cutover section) |
R3-Admin |
|
|
|
√10 PM – 2 AM (Sunday) |
Backup System (R-MAN) |
R3-Admin |
|
|
|
√ 10 PM - 1 AM (Sunday) |
Generate DB Statistics |
R3-Admin |
|
|
Sunday 12/12/10 (morning) |
√ 1 – 3 AM |
Transports Application (see detail cut-over project plan found on wiki in cutover section)
|
R3-Admin |
|
|
Post Upgrade Schedule and Processes |
|||||
Sunday |
√ 8 AM |
Validation reports executed (trial balance reports)
|
R3-Admin |
|
|
√ 10 AM |
Unlock web-services ids in Production |
R3-Admin |
|
||
|
√ 10 - 11 AM |
OAS Upgrade Project intersection (verify new OAS 10.1.3 is operational) |
Web Services |
|
|
|
√ By 11 AM |
Enable Gateways (SAPWeb/ESS) |
Web-tech |
|
|
|
√ By 11 AM |
Schedule EDI Job
|
R3-Admin |
|
|
|
√ By 11 AM |
Turn on the EDI “gourmet-1” server |
Enterprise Appl. Admin |
|
|
|
√ By 11 AM |
Email to ist-sap@mit.edu |
|
√ By 11 AM |
Switch ADS server connection back from J01 to J31 (updated version) |
R3-Admin |
|
|
|
√ 11 AM |
R3-Admin Action Log |
R3-Admin |
|
|
√ 12 PM -- |
|
√ By 2 PM |
Update voice message whether Data Validation is on schedule. |
Project Manager |
|
|
√ By 2 PM |
Unlock testers |
R3-Admin |
|
|
√ 2 PM -- |
PS1 Data Validations & Transaction processing listed in section 3 below performed by designated users; |
BPOs |
|
|
√ By 4 PM |
Coordinators for each area should send email to sap-validation-team@mit.edu at the completion of the validation notifying results |
BPOs |
|
|
√ 4 PM |
Conference Call Check-in |
Business Owners/ |
|
|
√ After con call |
Send e-mail to (sapbiz, sap-upgrade-core, ist-sap@mit.edu,warehouse@mit.edu, Elena@mit.edu,) notifying results. |
Project Manager |
|
|
8PM – 12AM |
Data Warehouse Job Validation |
√ 8PM – 10PM |
Unlock users (Facilities, SMART) |
R3-Admin |
|
||
|
√ 10 PM |
Enable Drop box |
Tech Services |
|
|
|
√ 10 PM |
Execute ProCard from Bank of America Feed |
Tech Services |
|
|
Monday |
√ 1:30 AM |
On Line back up of PS1 |
R3-Admin |
|
|
|
√ By 6 AM |
Update the 3-down web page & SAPgui message. |
R3-Admin |
|
|
√ By 6 AM |
Remove SAPweb, ESS and EHS messages |
Web Services |
|
||
√ 6 AM |
Email notification to the MIT Community stating the update is completed and Production is available. |
Project Manager |
|
||
|
√ 9 AM |
Reinstate weekend MITSIS Grad Appointment Feed |
Enterprise Appl. Admin |
|