1. Monday by 9am - Post messages on insideMIT, SAPweb and ESS (Employee Self Service) web sites about upcoming SAP outage.
2. Monday by 10am - Post message on ECAT web site about upcoming SAP outage.
3. Monday 10am - Begin online upgrade piece of the application of Enhancement Pack(s)
4. Monday 12pm - Post message on SAPgui indicating upcoming SAP outage
5. Monday by 5pm - Confirm that there are no GuiXT Changes
6. Monday by 5pm - Send message to MIT-SAP community about upcoming SAP outage.
7. Tuesday 10:30am - Cutover weekend planning meeting IS&T.
8. Tuesday 12pm - Steering Committee Meeting – review cut-over plan/ Go/No-go decision – W92
9. Tuesday by 5pm - Email Steering Committee Go/No-go decision
10. Wednesday 10:30am - 12pm - SAPbiz meeting to review the Production Cutover schedule and details, including action log and user support
11. Wednesday 2:00 - 3:00pm - Final review all issues in RT project queue, transport list, and web components.
12. Wednesday 3:00 - 4:00pm - SAP Action log team meeting to review the Production Cutover action log.