This folder contains current copies of relevant project schedules.  These schedules are attached in MSProject format an presented in HTML format.

High Level Plan for SAPBiz 10-22-08 v4

----| Project Start:
Project Finish: | Sat 9/20/08
Tue 12/23/08 |

Tasks


 ID

Task Name

Duration

Start

Finish

Resournce Names

% Complete

 

1

2008 Support Pack Implementation Project

65 days

Mon 9/22/08

Tue 12/23/08

 

0%

2

Project Prep

30 days

Mon 9/22/08

Fri 10/31/08

 

0%

3

PS1 Snapshot at end of day

0 days

Mon 9/22/08

Mon 9/22/08

 

0%

4

Transaction list available

0 days

Fri 9/26/08

Fri 9/26/08

R3

0%

5

Identify test scenarios / transactions

5 days

Mon 9/29/08

Fri 10/3/08

BUS,BA

0%

6

Review and update test scripts

20 days

Mon 10/6/08

Fri 10/31/08

BUS,BA

0%

7

SF3 Unavailable at end of day

0 days

Fri 10/10/08

Fri 10/10/08

 

0%

8

PS1 snapshot at end of day

0 days

Mon 10/20/08

Mon 10/20/08

R3

0%

9

Execute Trial balance for snapshot

0.5 days

Mon 10/20/08

Mon 10/20/08

BUS

0%

10

Save data warehouse extracts

0 days

Fri 10/10/08

Fri 10/10/08

DWH

0%

11

Support packs available from SAP

0 days

Mon 10/20/08

Mon 10/20/08

 

0%

12

PS1 Import 1

0 days

Thu 10/23/08

Thu 10/23/08

 

0%

13

SF3 System Refresh

5 days

Tue 10/14/08

Mon 10/20/08

 

0%

14

Refresh with 9/22/08 PS1 Snapshot

2 days

Tue 10/14/08

Wed 10/15/08

R3

0%

15

R3 Action Log

0.5 days

Thu 10/16/08

Thu 10/16/08

R3

0%

16

Scramble sensitive data

2.5 days

Thu 10/16/08

Mon 10/20/08

R3

0%

17

PS1 Snapshot at end of day

0 days

Mon 10/20/08

Mon 10/20/08

 

0%

18

Execute Trial Balance for later comparison

0.5 days

Mon 10/20/08

Mon 10/20/08

R3

0%

19

Support Packs available from SAP

0 days

Mon 10/20/08

Mon 10/20/08

 

0%

20

SFK Update

4 days

Tue 10/21/08

Fri 10/24/08

 

0%

21

Import Updates

1 day

Tue 10/21/08

Tue 10/21/08

R3

0%

22

Identify and resolve import issues

1 day

Wed 10/22/08

Wed 10/22/08

R3

0%

23

Validate security infrastructure (SNC)

1 day

Thu 10/23/08

Thu 10/23/08

R3

0%

24

Validate SAPGui interactions

0.5 days

Fri 10/24/08

Fri 10/24/08

R3

0%

25

Validate basic SAP functions work

0.5 days

Fri 10/24/08

Fri 10/24/08

R3

0%

26

PS1 Import - regular import cycle

0 days

Thu 10/23/08

Thu 10/23/08

 

0%

27

SF3 Update

5 days

Mon 10/27/08

Fri 10/31/08

 

0%

28

Import Updates

2 days

Mon 10/27/08

Tue 10/28/08

R3

0%

29

Execute action log

0.5 days

Wed 10/29/08

Wed 10/29/08

DEV,BA

0%

30

Update action log as necessary

0.5 days

Wed 10/29/08

Wed 10/29/08

DEV,BA

0%

31

Produce collision report

0.5 days

Wed 10/29/08

Wed 10/29/08

R3

0%

32

Review collision report

1 day

Wed 10/29/08

Thu 10/30/08

DEV,BA

0%

33

Reimplement MIT mods

1 day

Thu 10/30/08

Fri 10/31/08

DEV

0%

34

Confirm configuration steps work

0.5 days

Fri 10/31/08

Fri 10/31/08

DEV,BA

0%

35

Production Imports (last regular import cycle)

0 days

Thu 10/30/08

Thu 10/30/08

 

0%

36

Development slowdown starts

0 days

Fri 10/31/08

Fri 10/31/08

 

0%

37

Unit Test Preparation and Execution

6 days

Mon 11/3/08

Mon 11/10/08

 

0%

38

Apply support packs to SF2

2 days

Mon 11/3/08

Tue 11/4/08

R3

0%

39

Update and Execute action log

0.5 days

Wed 11/5/08

Wed 11/5/08

BA,DEV

0%

40

Import transports from SF3

0.5 days

Wed 11/5/08

Wed 11/5/08

R3

0%

41

Unit test, resolution and retest in SF2

3 days

Thu 11/6/08

Mon 11/10/08

BA,DEV

0%

42

System Test / User Acceptance Test Environment Preparations

10 days

Mon 10/27/08

Fri 11/7/08

 

0%

43

Refresh TST with 10/20 snapshot, NO SCRAMBLING DATA

3 days

Mon 10/27/08

Wed 10/29/08

R3

0%

44

Import post snapshot production transports (delta from 10/20 to 10/30)

2 days

Thu 10/30/08

Fri 10/31/08

R3

0%

45

Import updates

2 days

Mon 11/3/08

Tue 11/4/08

R3

0%

46

Import SF3 transports & post-update DEV transports (to be tested during SI & UAT)

1 day

Wed 11/5/08

Wed 11/5/08

DEV

0%

47

Execute trial balance and compare with TB from 10/20

0.5 days

Thu 11/6/08

Thu 11/6/08

BUS

0%

48

Execute action log

0.5 days

Thu 11/6/08

Thu 11/6/08

DEV,BA

0%

49

Execute DWH extracts and comparison

1 day

Fri 11/7/08

Fri 11/7/08

DWH

0%

50

Execute System Integration Tests

6 days

Wed 11/12/08

Wed 11/19/08

 

0%

51

HR-Payroll

6 days

Wed 11/12/08

Wed 11/19/08

DEV,BA

0%

52

Logistics

6 days

Wed 11/12/08

Wed 11/19/08

DEV,BA

0%

53

EHS

6 days

Wed 11/12/08

Wed 11/19/08

DEV,BA

0%

54

Financial

6 days

Wed 11/12/08

Wed 11/19/08

DEV,BA

0%

55

Execute User Acceptance Test (UAT)

15 days

Thu 11/20/08

Fri 12/12/08

 

0%

56

Execute UAT

9 days

Thu 11/20/08

Thu 12/4/08

BUS

0%

57

Financial Close

2 days

Fri 12/5/08

Mon 12/8/08

BUS

0%

58

Issue retesting

2 days

Tue 12/9/08

Wed 12/10/08

ALL

0%

59

Execute another financial close?

1 day

Thu 12/11/08

Thu 12/11/08

BUS

0%

60

UAT sign off

1 day

Fri 12/12/08

Fri 12/12/08

ALL

0%

61

Cutover weekend & Controlled Start

2 days

Sat 12/13/08

Sun 12/14/08

ALL

0%

62

Drop Dead Date for support packs in production

0 days

Mon 12/22/08

Mon 12/22/08

 

0%

63

First Calendar 2009 Payroll

0 days

Tue 12/23/08

Tue 12/23/08

 

0%

 