IS&T Change Communications Report April 11, 2012 |
|
|
|
|
|
||
|
|
|
|
|
|
|
|
Service Offering |
Tier |
Change |
Date |
Outage |
Time |
Status |
|
IPTV |
PROD |
Access for all undergraduate students - completed |
Week of 4/9/12 |
N |
|
TBD |
|
Tivoli Storage Manager (TSM) |
PROD |
Upgrading TSM-i - No customer facing servers |
4/11-4/12 |
Y |
|
SCHED |
|
SAP |
PROD |
Administrative Systems - F5 changes to sky-app 21 and 22 to enhance load balancer routing functionality |
4/13/12 |
N |
|
SCHED |
|
Unity |
PROD |
Transition DLCs to new voicemail system |
4/14-4/15/12 |
N |
|
SCHED |
|
Stellar |
PROD |
Stellar Classic - Update 2.3.8 |
4/21/12 |
y |
7-8 am |
SCHED |
|
Unity |
PROD |
Iperia accounts will be decommissioned on 4/30. Voicemail broadcast was sent on 4/9/12 |
4/30/12 |
N |
|
SCHED |
|
Electronic Transcripts |
PROD |
Enhancements |
April |
N |
|
TBD |
|
Mobile Web |
PROD |
Update to mobile platform |
April |
N |
|
TBD |
|
Online Grading |
PROD |
Enhancements - delayed until next week |
April |
N |
|
TBD |
|
SAP Enterprise Learning (eLearning) |
DEV |
F5 changes to eliminate port 5661 reference and to route from standard ports to non-standard ports |
April |
N |
|
TBD |
|
Distributed Software |
DEV |
IDFinder 5.7: installer completed. Move to test in next few weeks |
April |
N |
|
TBD |
|
SAP Requisitions |
PROD |
Attachment functionality available (Open Text) |
5/7/12 |
N |
|
SCHED |
|
IPTV |
PROD |
Graduate student access |
May |
N |
|
TBD |
|
SAP Hourly Student Appointments |
DEV |
Enhancements - functionalities will be added |
May-June |
N |
|
TBD |
|
MIT SECURE |
PROD |
Radius servers to point to Exchange Active Directory |
|
N |
|
TBD |
|
MIT SECURE |
PROD |
Open Wireless retirement |
|
N |
|
TBD |
|
Distributed Software |
PROD |
Decommissioning older versions of SAPgui for both Mac and Windows |
|
N |
|
TBD |
|
VPN |
PROD |
Legacy application (native client) to be retired |
|
N |
|
TBD |
|
Distributed Software |
TEST |
Office for Students: perpetual license activation script |
|
N |
|
TBD |
|
Casper |
TEST |
Managed environment for Mac |
|
N |
|
TBD |
|
MIT SECURE |
DEV |
Exploring auto configuration tools for computers |
|
N |
|
TBD |
|
Macintosh Support |
DEV |
OS X 10.8 developer preview (Mountain Lion) |
|
N |
|
TBD |
|
WebEx |
DEV |
Mac bug in Events Center and Training Center |
|
N |
|
TBD |
|
Distributed Software |
DEV |
Evaluating Windows 8 developer preview (internal to IS&T only due to NDA) |
|
N |
|
TBD |
|
Wikis (MIT Wiki Service) |
DEV |
Will archive older spaces in July (initial communications will be sent out week of 4/16/12) |
July |
N |
|
TBD |
|
SAP |
DEV |
Portal support package upgrade for Netweaver and Stock level 7 components |
|
|
|
TBD |
|
|
|
|
|
|
|
|
|
Status Key: |
|
|
|
|
|
|
|
SCHED |
Scheduled routine maintenance |
|
|
|
|
|
|
EMER |
Emergency change - problem if not addressed |
|
|
|
|
|
|
LOW |
Outage or problem with low user impact |
|
|
|
|
|
|
HIGH |
Outage or problem with high user impact |
|
|
|
|
|
|
TBD |
Exact change date or time to be determined |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Business Events to keep in mind:
- SW Development Time Allocation Draft Report 4/17/12
- Drop date: 4/26/12
- SW Development Time Allocation Final Report 4/27/12
- Last day of classes 5/17/12
- Final exams 5/22-5/29/12
- Administrative Staff Performance Assessment due 6/8/12
- Commencement 6/8/12