High-Level Timeline
Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
10/09/2014 - SAP release of year end base level support pack
10/20/2014 - End of day production snapshot to be used to refresh test environments
- Development Freeze begins
- Last date to implement support & enhancement changes until freeze ends on
Unit test
System Integration Test (regression test fixes: )
12/05/2014 - Go-live weekend!
- Development Freeze ends