High-Level Timeline
Now thru the end of October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
10/09/2014 - SAP release of year end base level support pack
10/20/2014 - End of day production snapshot to be used to refresh test environments
10/20/2014 - Development Freeze begins
10/30/2014 - Last date to implement support & enhancement changes until freeze ends on
10/24/2014 - Unit test
11/03/2014 - System Integration Test (regression test fixes: )
12/05/2014 - Go-live weekend!
12/10/2014 - Development Freeze ends