Touchstone Functional Testing - Phase 1 - Test Plan

1.0 Document identifiers

1.1 Document Author

The document author is:

Author

Title

Telephone

Email Address

Will Smithee

Senior Practice Manager

336-232-5208

will_smithee@questcon.com

1.2 Document Revisions

Issue

Date

Author

Reason for Change

0.1

01/27/2008

Will Smithee

Initial draft

 

 

 

 

1.3 References

The following documents were used as sources of information for this test plan:

2.0 Introduction

2.1 Purpose

The objective of this test plan is to outline the functional testing effort to be undertaken for the Touchstone project.

2.1.1 Project Description

MIT Touchstone is a new suite of technologies for authenticating a variety of web applications, being introduced by IS&T. MIT Touchstone does provide a single sign-on solution for applications that have been coded and configured to use the system. Within the context of Touchstone enabled applications, users will be able to seamlessly transition between systems without being prompted for additional authentication information.
The intended audience of this document includes all IT personnel involved in the development, testing, and support of Touchstone.

2.1.2 Project Technologies

MIT Touchstone utilizes/integrates with the following technologies:

2.2 Scope

2.2.1 Items To Be Tested

Each of the following UI components and front end functionality developed as part of the Touchstone project will be tested:

2.2.2 Items Not To Be Tested

The following modules and types of tests are considered to be outside the scope of this test effort and will not be tested by Questcon.  Testing will be performed by internal MIT personnel:

2.3 Risks & Contingencies

The following risks have been identified, which may impact the testing effort.

Risk

Contingency

QA environment not available

Utilize development or production environment

Insufficient time to fully test the Touchstone application with all major web browsers

Execute ~80% of application functionality with MIT's standard browser (Mozilla Firefox 2.0) and ~20% of the functionality with other browsers.

Test time increases due to changes in scope requiring additional test analysis and/or test case creation

If test time cannot be increased, reduce/cut overlap in multi-browser testing and execute highest priority test cases initially followed by lower priority tests until test time runs out

Excessive defect rate or defect correction time

Execute test cases in unrelated/unblocked functional areas of the application based on designated priority

3.0 Approach

3.1 Testing Strategy

The overall approach to this test effort will be to validate that the Touchstone UI meets the needs of the user community as a tool for managing images and other digital media.  Validation will be performed based on test cases derived from the documented use cases, front-end functional designs, as well as exploratory testing heuristics.
MIT has indicated that the user community is largely standardized on Mozilla's Firefox v2.0 web browser in a PC or Mac environment.  Rather than re-executing all tests with each browser, Questcon will execute approximately 80% of the test cases using Firefox and approximately 20% of the tests using IE 6 and 7 (both in a PC/Windows architecture).  There will be some overlap in testing and touch points, but not enough to significantly impact the schedule.
Questcon will analyze the test cases to identify the best candidates for execution using IE 6 and 7.  IE 6 and 7 test cases will be chosen based on the amount of functionality traversed in the application.  In other words Questcon will attempt to "touch" as much of the application as possible using IE 6 and 7. 
Furthermore, a significant portion of the user community utilizes the Mac OS X operating system with the Safari browser.  Some duplicate testing will be performed by Questcon utilizing Safari and Firefox for the Mac (10% or less).  MIT should designate a group of users to execute more tests using the Safari/Mac and Firefox/Mac combination of browser and operating system.  Questcon will assist the users in identifying the best tests to execute.
The following table outlines the various types of testing considered for this test effort, any additional comments about the testing, and the individual or group responsible for completing the testing.

Type of Testing

Included
Y/N

Comments

Team Responsible

Automation

Y

MIT personnel will utilize jMeter to automate portions of the backend testing; no test automation tools will be used for the UI testing (use of Flash prevents this).

MIT - Tester

Conversion

N

There is no pre-existing system, therefore no data conversion is necessary.

N/A

Exploratory

Y

Some level of exploratory testing will be conducted based on heuristics related to typical rich-content internet applications.

Questcon

Functional

Y

Functional testing will be performed based on test cases derived on the documented use cases and front-end functional design.

Questcon

Installation / Upgrade

N

Because this is a web application no installation testing is necessary.

N/A

Integration

Y

Some integration testing will naturally occur as the front-end of the Touchstone application interfaces with and utilizes the back-end APIs.

Questcon

Parallel

N

There is no existing system that Touchstone is replacing.

N/A

Performance

Y

Performance testing will be done on the back-end APIs and servlets.  No front-end performance testing will be done.

MIT - Tester

Regression

Y

Questcon expects to run at least a minimum regression test set prior to release to production.

Questcon

Security

Y

Backend security testing will be done by MIT.  Questcon will execute basic security/login testing on the front-end

MIT - Tester (backend)
Questcon (front-end)

UAT

Y

The user community will be tasked with performing ad-hoc user acceptance testing, domain specific metadata testing (metadata titles, tag lists, etc.),  as well as previously designated documented functional test cases for multiple browser/OS configurations (primarily Safari or Firefox/Mac configurations).

MIT - User Community

Unit

Y

Questcon expects the MIT developers to perform unit testing prior to releasing code to the test environment.

MIT - Developers

3.2 Tools

The following tools will be used as part of the overall Touchstone testing effort:

Tool

Purpose

Used By

Atlassian Jira

Web-based defect tracking system accessed by http://bazim.mit.edu:8080/jira

Touchstone Project Team (MIT & Questcon)

Apache JMeter

Backend performance testing

MIT - Tester

3.3 Environmental Needs

Questcon anticipates the following server and client configurations for the QA environment:

3.3.1 Web Server Configuration

The QA environment web server may be accessed via:
Secure certificate servers
????
Non-certificate servers
????

Hardware

O/S

Other

TBD

TBD

  • Apache ???
  • Tomcat ???
  • Openssl ???
  • Mod-jk ???
  • Jdk ???
  • ???

3.3.2 Repository Server Configuration

Hardware

O/S

Other

HP G4

Red Hat Enterprise Linux AS release 4

  •          Alfresco 2.0.1 Enterprise

3.3.3 Database Server Configuration

Hardware

O/S

Other

HP G4

Red Hat Enterprise Linux AS release 4

  •          Oracle 10g

3.3.4 Client Configuration

Hardware

O/S

Other

PC

Windows XP Professional SP 2

  • Mozilla Firefox v2+
  • Microsoft IE v6+
  • Adobe Flash v9+1

Macintosh PowerPC

Mac OS X

  •          Firefox v2+
  • IE v6+
  • Flash v9+ 
  • Safari v2+

4.0 Schedule of Deliverables and Resources

4.1 Deliverables

This section identifies the deliverables, delivery date and resource responsible for each deliverable.
Key Deliverables
Expected Delivery Date
Resource

Functional Test Tree

05/04/2007

Bill Silver

Test Plan

05/07/2007

Shaun Bradshaw

Test Case Designs

05/14/2007

Sylvia Stanfield

Test Cases

05/28/2007

Sylvia Stanfield

Status Reports

Weekly

Shaun Bradshaw

Test Logs

Ongoing during test execution

Sylvia Stanfield

Defect Reports

Ongoing during test execution

Sylvia Stanfield, Shaun Bradshaw

Test Summary Report

07/17/2007

Shaun Bradshaw

4.2 Test Schedule

The planned test schedule of the Touchstone project has an anticipated start date of 04/25/2007 and completion date of 07/17/2007.  The estimated completion date is based on several assumptions, some of which have been identified in 2.3 Risks & Contingencies
Milestone
Target Timeframe
Summation of Activities

Develop test strategy / plan

04/25/2007 - 05/07/2007

  •          Analyze existing design documents, notes, and other available materials