Cutover Document Links:
| 2017 SAP SP Cutover Plan | FLE Validations | HRP Validations | PS1 User List |
|---|
Project cut-over status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/8 through noon on Monday 12/11. The Project Manager will update this message as needed. A conference call number (webex) is available for check-ins during the weekend and for the Go/No Go call at 6:00pm on Sunday.
All tasks scheduled for execution through Thursday 12/7 are complete.