Alternate High-Level Timeline #1

(tick) September thru the end of October - Plan, create/update test scripts in ALM, move pending support & project work into production.
(tick) 10/11/2018 - SAP release of year end base level support pack
(tick) 10/18/2018 - Last date to implement support & enhancement changes until freeze ends on 11/21/2018
(tick) 10/19/2018 - Development Freeze begins
(tick) 10/22/2018 - End of day production snapshot to be used to refresh test environments (9/24 for SF3)
(tick) 10/24/2018 - Unit test

(tick) 11/01/2018 - 11/02/2018 Controlled Payroll Runs (SH2)

(info) 11/01/2018 - 11/09/2018 (7 business days) - System Integration Test (regression test fixes: 11/12-13/2018)

(info) 11/16/2018 - Go-live weekend! (start Friday at 5pm)

(info) 11/21/2018 - Development Freeze ends

(lightbulb)

Alternate High-Level Timeline #2

(tick) September thru the end of October - Plan, create/update test scripts in ALM, move pending support & project work into production.
(tick) 10/11/2018 - SAP release of year end base level support pack
(tick) 10/22/2018 - End of day production snapshot to be used to refresh test environments (9/24 for SF3)
(info) 10/31/2018 - Last date to implement support & enhancement changes until freeze ends on 12/12/2018
(info) 11/01/2018 - Development Freeze begin
(info) 11/06/2018 - Unit test

(info) 11/14/2018 - 11/15/2018 Controlled Payroll Runs (SH2)

(info) 11/14/2018 - 11/30/2018 (11 business days) - System Integration Test (regression test fixes: 12/3-4/2018)

(tick) 12/07/2018 - Go-live weekend! (start Friday at 5pm)

(tick) 12/12/2018 - Development Freeze ends