Cutover Document Links
| 2018 SAP SP Cutover Plan | 2018 FLE Validations | 2018 HRP Validations | 2018 PS1 User List | Temporary FF Access Procedure |
|---|
Project cut-over status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/7 through noon on Monday 12/10. The Project Manager will update this message as needed. A conference call number (webex) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
| The PS1, GRC and SAP Mobile upgrades are complete. Post upgrade activities in these environments are complete or near completion. All indications are that we are on schedule for validations on Sunday morning. |
|---|