Cutover Document Links

2018 SAP SP Cutover Plan2018 FLE Validations2018 HRP Validations2018 PS1 User List Temporary FF Access Procedure
The following is a copy of the Support Pack Implementation (cut-over) Plan:

Communication

Project cut-over status of the upgrade, see below,  will be posted on this wiki page beginning at noon on Friday 12/7 through noon on Monday 12/10.  The Project Manager will update this message as needed.  A conference call number (webex) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.

Project Status: 
Sunday 12/9: Validations are complete.

Conference Call Line: Webex Audio