High-Level Timeline
Now and thru the end of October -
Plan, create/update test scripts in ALM, move pending support & project work into production.
10/10/2019 - SAP release of year end base level support pack
10/17/2019 - Last date to implement support & enhancement changes until freeze ends on 12/10
10/18/2019 - Development Freeze begins
10/21/2019 - End of day production snapshot to be used to refresh test environments (10/1 for SF3)
10/23/2019 - Unit test
11/01/2019 - 11/02/2019 Controlled Payroll Runs (SH2)
11/04/2019 - System Integration Test (regression test fixes: 11/28-29/2019)
12/06/2019 - Go-live weekend! (start Friday at 5pm)
12/10/2019 - Development Freeze ends