sml -- I reformatted Catherine's notes into concrete requirements and tasks for the team. Some of these will copy to the Product backlog or into specific Sprint documentation.

Important Dates

June 15: Clearspace environment setup, tentative experiments connecting to an existing LDAP directory operated by NIST, determination of "least amount of work" path, recommendations
Clearspace to QA: July 15
Clearspace production date: August 1.

Questions to Answer for ISDA Lead Architects

New Requirements

Impediments: Product Owner Tasks (Steve Landry and Possibly Derek Jaeger)