High-Level Timeline
By end-of-day Nov 4 - Plan, create/update test scripts in ALM. (SAP Business Areas)
End of day production snapshot from 9/19/2022 to be used to refresh SF3 environment
End of day production snapshot from 9/17/2022 to be used to refresh SH1 environment
End of day production snapshot from 10/17/2022 to be used to refresh SH2 environment
Refer to calendar for detailed time frames
2022 SAP Support Pack Upgrade - Calendar View
Oct 6: SAP releases year-end support pack versions
Oct 14-19: SF3 upgrade
Oct 17: SH1 ready for use
Oct 23 at 5PM: start of SF2 restricted window
Oct 24-26: SF2 upgrade
Oct 25 at 5PM: start of SH2 restricted window
Oct 26-Nov 1: SH2 refresh and upgrade
Nov 3-4: IS&T Controlled Payroll Test
Nov 7-29: SH2 business testing
Nov 30 -Dec 2 - Uptime Production Cut-over Activities -
Dec 2-Dec 4 - Go-live weekend! (start Friday at 5pm)
Dec 5 - Upgraded PS1 is ready for use
---------
SAP Scheduled Upgrades - Ancillary Systems
ERP Target
ERP:
NetWeaver/GRC:
NetWeaver/ADS:
SAP Mobile: