2022 SAP Support Pack Cutover Plan
2022 FLE Validations
2021 Final Post Upgrade Transport List - to be updated by Elda
Project cutover status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/2/2022 through noon on Monday 12/5/2022. The Project Manager will update this message as needed. A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
| Thu 11/10/22 11:00AM: Business Team Regression Testing underway in SH2 |
|---|