The following is a copy of the Support Pack Cut-over and Test Plans:

2022 SAP Support Pack Cutover Plan

2022 FLE Validations

2022 HRP Validations

2022 PS1 User List

2021 Final Post Upgrade Transport List - to be updated by Elda

Communication

Project cutover status of the upgrade, see below,  will be posted on this wiki page beginning at noon on Friday 12/2/2022 through noon on Monday 12/5/2022.  The Project Manager will update this message as needed.  A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.

Project Status: 
Thu 11/29/22 9:00AM:  Final cutover preparations are being performed.  On track for Production update 5pm Friday (12/2) to 6am Monday (12/5)

Conference Calls (Zoom) for cut-over weekend: