2022 SAP Support Pack Cutover Plan
2022 Final Post Upgrade Transport List
Project cutover status of the upgrade, see below, will be posted on this wiki page beginning at noon on Friday 12/2/2022 through noon on Monday 12/5/2022. The Project Manager will update this message as needed. A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.
Sunday 12/04/22 7:45 AM: PS1 systems validations by IS&T begin at 8:30am this morning; followed by Business Team validations at 10:30am. |
|---|