0) Executive Summary


1) Scope, Assumptions, and Interfaces


2) Life-Cycle Phasing & Reviews (Entry/Exit Criteria)

Pre-Phase A — Concept Studies

Objectives

Phase A — Concept & Technology Development

Objectives

Phase B — Preliminary Design & Technology Completion

Objectives

Phase C — Final Design & Fabrication

Objectives

Phase D — System Assembly, Integration, Test, and Launch

Objectives

Phase E — Operations & Sustainment

Objectives

Phase F — Closeout & Disposal

Objectives


3) Systems Engineering Management (SEMP) Content

3.1 Technical Baseline & Requirements

3.2 Architecture & Design

3.3 Verification & Validation (V&V)

3.4 Integration & Test (I&T / AIV)

3.5 Safety, Mission Assurance, & Cyber

3.6 Project Management


4) Rideshare-Specific Planning


5) Budgets & Margins (living documents)

BudgetOwnerv1 DueExit SRRExit PDRExit CDRAcceptance
Mass (incl. fasteners)SE+20%+15%+10%+5%
Power (peak/avg, inrush)EE+30%+25%+20%demo’d
Thermal (hot/cold cases)Thermalworst-caserefinedcorrelatedcorr. to TVAC
Data rate/volume/latencySW/RFlink margin ≥3 dBpacket loss spec’dE2E testedops proven
Pointing/jitter (if needed)GNCreqs setmodelledverifiedon-orbit

(Tailor margins to your center/host standards.)


6) Verification Cross-Reference Matrix (VCRM) — Skeleton

Req IDRequirement (shall)V-MethodLevelEnvironment/ConfigSuccess CriteriaReview Gate
SYS-PWR-001Payload peak power ≤ 35 W for <10 s; avg ≤ 12 WTSystemHot TVAC, max duty cycleMeasured ≤ limitsTRR/FRR
SYS-EMC-010Conducted emissions meet host spec §X.YTSystemEMC chamberWithin limitsTRR
SYS-THERM-020CBE temps within -10…+40 °CA/TSubsys/SystemThermal model + TVACMargins ≥ 5 °CCDR/FRR
SW-LAT-100Cmd→resp latency ≤ 200 msTSystem HILWorst-case load≤ 200 msORR

7) I&T Flow (high level)

  1. Unit functional → 2. Subsystem functional + HIL → 3. System functional

  2. EMI/EMC pre-screen (optional but recommended)

  3. Environmental qual (vibe/acoustic/shock → TVAC → EMC)

  4. Final functional & workmanship inspection

  5. Pre-ship review (PSR)Ship to integrator

  6. Host fit-checkInterface testsFRRLaunch site ops


8) Ground Segment & Operations (Phase E)


9) Regulatory, Export, and Safety


10) Risk, Opportunity & Issue Management

Likelihood (L) × Consequence (C), 5×5 matrix; risk burn-down reviews biweekly.

IDRiskCauseLCMitigationTriggerOwner
R-01ICD change lateHost redesign34Reserve mass/power; adapter plate; buffer in harness lengthsICD rev > PDR+1SE
R-02EMC failureSwitching noise25Spread-spectrum, filters; pre-screenPre-screen > −6 dB marginEE
R-03Export delayLicense lead time33Early application, alternate site planT-L-120dPM

11) Configuration & Data Management


12) Team, WBS, and RACI (sample)

Core roles: PM, SE, EE, ME, Thermal, RF/Comms, SW/FPGA, AIV Lead, SMA/QA, Regulatory, Ops, Supply Chain.

TaskPMSEEEMESWAIVSMAReg
ConOps/ReqsARCCCCCC
ICD w/ HostCRRRCCCC
BudgetsCRRRRCC
V&V/VCRMCRCCCRC
I&T PlanCRCCCRC
RegulatoryCCR

(R=Responsible, A=Accountable, C=Consulted, –=None)


13) Schedule Backbone

Milestone Backbone

Nov 20, 2025 — PDR. Phase B wrap; ICD v0.8; budgets v1 locked.
Nov 25–Dec 5, 2025 — Long-lead POs. (radiation-tolerant parts, custom PCBs, optics, harness).
Jan 15, 2026 — CDR. Detailed design released; ICD v1.0 for host.
Jan 16–Feb 12, 2026 — Fabrication & assembly (EDU/Flight).
Feb 3–Feb 21, 2026 — Bring-up & unit functional.
Feb 17–Mar 3, 2026 — System integration & HIL.
Feb 24–Feb 27, 2026 — EMI/EMC pre-screen.
Mar 4, 2026 — TRR.
Mar 5–Mar 30, 2026 — Qualification campaign.

Tracks & owners (what runs in parallel)

Reserves & assumptions


14) Deliverables Checklist by Review

SRR: ConOps, SRD, ICD v0.5, SEMP, Budgets v1, V&V strategy, Risk Log v1, SMA plan, Software plan, Regulatory plan.
PDR: Preliminary design package, ICD v0.8, VCRM v1, I&T plan draft, Environmental plan draft, FMEA/PHA, Long-lead list, Updated budgets, Config & QA plans.
CDR: Released drawings/BOMs, Software detailed design, ICD v1.0 (signed), Test procedures, VCRM v2 with acceptance criteria, Safety updates, Manufacturing plans.
TRR: Test procedures approved, calibrated EGSE, configs frozen, hazards closed to test.
FRR/PSR: All test reports with closures, NCRs dispositioned, as-built EIDP, shipping plan, site procedures, operations handbook draft.
ORR: Commissioning procedures, anomaly rules, ground readiness, data pipeline validated.


15) Immediate Next Actions (you can start these today)

  1. Draft one-page ConOps (user goals, timelines, operating modes).

  2. Start ICD assumption sheet from host/deployer datasheets (envelope, power, data, EMC).

  3. Stand up risk log and budget workbook (mass/power/thermal/data).

  4. Create SEMP v0.1: org/RACI, review calendar, V&V philosophy, CM & QA, regulatory path.

  5. Identify long-leads (radiation-tolerant parts, precision optics, custom PCBs, HV supplies).

  6. Put hard anchors on the schedule: ICD freeze date, DDI (delivery), FRR window.