Key dates
Support Pack Project
	- Now - October - Plan, create master script catalog, improve test scripts, move pending work to production
 
	- 10/05/2009 - Last date to implement projects until freeze ends on 12/24/2009 (Except Open Enrollment & Union Structures)
 
	- 10/22/2009 - Last date to implement support & enhancement changes until freeze ends on 12/24/2009
 
	- 11/09/2009 - 11/22/2009 System Integration Test
 
	- 11/23/2009 - 12/09/2009 User Acceptance Test
 
	- 12/11/2009 - 12/13/2009 Golive Weekend
 
	- 12/24/2009   Freeze ends
 
Open Enrollment & Union Structures
	- 09/15/2009 - 10/01/2009 System Integration Test
 
	- 10/01/2009 - 10/31/2009 User Acceptance Test
 
	- 11/02/2009 - 11/06/2009 Pilot Open Enrollment
 
	- 11/09/2009 - 11/20/2009 Community Open Enrollment
 
	- 12/06/2009   Vendor Extracts
 
Summary Plan

Monthly Priorities & Deliverables
 
 Month     | 
 Major Deliverables     | 
 Responsible     | 
 August   | 
	- Plan, resources, kickoff
 
	- QA instructions, templates
 
	- Test scope defined
 
	- Consolidated master test catalog
 
 
 | 
	- Bart
 
	- Wendy
 
	- Core Team - Functional / Wendy
 
	- Core Team - Functional
 
 
 | 
 September   | 
	- Pending work moved to production
 
	- Updated test scripts
 
 
 | 
	- Core Team - Functional
 
	- Core Team - Functional
 
 
 | 
 October   | 
	- System preparation
 
 
 | 
	- Core Team - Technical
 
 
 | 
 November   | 
	- Unit Test
 
	- System Integration Test
 
 
 | 
	- Core Team - Technical/Functional
 
	- Core Team - Functional
 
 
 | 
 December   | 
	- User Acceptance Test
 
	- Production
 
 
 | 
	-  Business Owners
 
	- All
 
 
 | 
Current Detail Plan
TBD - process, environment, plan to allow project work development and testing to move through landscape immediately following support pack work.