Presentations 
Meeting Notes
09/13/2010 - Core Team Meeting
In attendence: core team members
Agenda
- Set schedule date and time for core team meetings
- consensus to meet Monday's at 10:00-11:00am for the duration of the project; location W92:Downtown Crossing
- Review of detail project plan
- discussion around practice system
- discussion around transports
- discussion around testing
- discussion around freeze
- Next steps
- focus on test plan
- confirm NW 7.0 EHP 2 availability & compatibility (Bart & Ron are pursuing with SAP)
- focus on moving current development work to production
- SAPbiz meeting on 9/22/2010
09/09/2010 - IS&T Kickoff Meeting
In attendence: ist-sap list members
Agenda
- Background
- Project Organization
- Project wiki
- Project Risks
- Important Dates
- Next Steps
Meeting presentation is attached above.
09/07/2010 - SP Steering Committee
In attendence: Bart Dahlstom, Frank Quern, Gerry O'Toole, John Doyle, Magdalene Lee, Mary Weiss, Steve Buckley, Wayne Turner
Agenda
- Background
- Project Scope
- Project Organization
- High Level Time Line
- Project Risks
- Roles & Responsibilities
- Important Dates
- Next Steps
Meeting's presentation is attached above.
The general consensus is to move forward with the project as planned.