The PMBA Working Group will focus on the planning phase of the project lifecycle for the next twelve months. Below is a list of potential deliverables for the Working Group to consider:
Initial Work
- Finalize charter and communicate out
- Explore collaborations with Facilities PIT Team
- Explore collaborations with Lincoln Labs PMO
- Identify what has worked in the past and why
- Discussion of what has not worked in the past and why
- Review of existing processes in use in parts of IS&T
- Identify gaps in practice
- Determine projects to pilot practices and get feedback
- Explore ways to roll out deliverables
Future Products
- Definition of team member roles and responsibilities for our customers (including sponsors and stakeholders)
- Improved stakeholder analysis (identification, classification) and engagement and communication tools
- Tool Inventory
- Project Review Improvements
- Project Lifecycle At-A-Glance “cheat sheet”
- Budget and time allocation
- Introduction to User Experience Design
- Introduction to Usability and Accessibility
- Business case template
- Project Kick off and communication plans
- Scope and budget development guidelines
- Introduce conceptual model as part of design (where applicable)
- Project Kick Off checklists
- Communication Plans (templates)
Membership FY2011
Name |
Area |
Wendy Bastos |
Systems Engineering |
Deb Bowser |
Operations & Infrastructure |
Myra Hope Eskridge |
Systems Engineering |
Marco Gomes |
Operations & Infrastructure |
Amon Horne |
Data Management |
Barbara Johnson |
Customer Support |
Bill McAvinney |
Systems Engineering |
Karon McCollin |
Administrative Systems |
Kevin Mullins |
Operations & Infrastructure |
Anne Silvester |
Operations & Infrastructure |
Lori Singer |
Education Systems |
Joanne Stevenson |
Educations Systems |
Patricia Sheppard |
Administration |