The transport tracking goal is to move as much pending work to production as soon as possible, before the Monday 5:00 pm 10/20/2025 production restricted window (the instructions for how to derive the details for the table below can be found by following the Transport Coordinator Instructions & Audit Process link on previous page in project Wiki).
| Transport status | # of Transports as of 10/02/26 | # of Transports as of 10/09/26 | # of Transports as of 10/16/26 | # of Transports as of 10/23/26 | # of Transports as of mm/dd/yy |
| SF2 transports not released | 108 | 106 | 108 | 109 | |
| SF2 Released not in SH2 | 242 | 242 | 241 | 243 | |
| SF2 Released in SH2 not in PS1 | 86 | 70 | 70 | 61 | |
| SF3 Mods in SF2 not in SH2 | 4 | 4 | 4 | 4 | |
| SF3 Mods in SF2 SH2 not in PS1 | 0 | 0 | 0 | 0 |
See attached spreadsheets below for details.
SP2026 Open Transports 20261023.xlsx
SP2026 Open Transports 20261016.xlsx
SP2026 Open Transports 20261009.xlsx
SP2026 Open Transports 20261002.xlsx