The following is a copy of the Support Pack Cut-over and Test Plans:

2026 SAP Support Pack Cutover Plan

2025 FLE Validations

2025 HRP PS1 Business Validations.xlsx

2025 PS1 User List

2025 Final Post Upgrade Transport List  

Communication

Project cutover status of the upgrade, see below,  will be posted on this wiki page beginning at noon on Friday 12/4/2026 through noon on Monday 12/7/2026.  The Project Manager will update this message as needed.  A conference call number (zoom) is available for check-ins during the weekend and for the Go/No Go call at 1:00pm on Sunday.

Project Status: 

Monday 12/7/2026 6:00 AM:  SAP Support Pack update is expected to be complete and PS1 available to the MIT Community.

Conference Calls (Zoom) for cut-over weekend:

  • Saturday 4:30PM IS&T 
  • Sunday 1PM Validation review