0) Executive Summary

  • Mission goal: Increase the Technology Readiness Level (TRL) of a propellant mixing sytem that can be used to reduce temperature stratification in propellant tanks.

  • Mission class & context: Secondary payload on a rideshare mission to Low Earth Orbit (LEO), hosted by Oligo Space

  • Top risks: Host ICD change risk; late rideshare manifest changes; export/licensing; EMI/EMC with host; data rate/power shortfalls.

  • Key dates: LV environments/ICD freeze; PDR/CDR; payload delivery for I&T; environmental test window; ship to integrator; launch campaign; commissioning; ops end.


1) Scope, Assumptions, and Interfaces

  • Scope: End-to-end delivery of a flight-ready payload + EGSE/MGSE, software, procedures, and ops support until decommissioning.

  • Assumptions:

    • Rideshare provides: Anything we need for integration 

    • Payload class/size: e.g., hosted (bolted to bus)

    • Data path: (TBD)

  • Primary Interfaces: (TBD)


2) Life-Cycle Phasing & Reviews (Entry/Exit Criteria)

Pre-Phase A — Concept Studies

Objectives

  • Establish mission need, stakeholder set, and high-level ConOps; identify rideshare options; rough cost/schedule.
    Artifacts

  • Mission Need Statement; Concept of Operations (ConOps); trades (hosted vs deployed, frequency band, ADCS needs); straw-man ICD assumptions; ROM cost/schedule; risk register v0.1.
    Gate/Review: MCR (Mission Concept Review)
    Exit criteria: Selected concept, draft high-level requirements, resourcing for Phase A.

Phase A — Concept & Technology Development

Objectives

  • Refine ConOps, define Level 1/2 requirements, close key feasibility risks, pick subsystem architectures, long-lead planning.
    Artifacts

  • SEMP (Systems Engineering Management Plan), Stakeholder Expectations, System Requirements (SRD), Initial Verification Strategy (methods: test/analysis/inspect/demo), Preliminary ICD with host/deployer, Risk, Opportunity & Issue (ROIL) Log, Technology maturation plan, Preliminary MEL/PEL, mass/power/thermal/link budgets v1, Safety & Mission Assurance (SMA) plan, Software Plan (standards, IV&V as needed), Cybersecurity tailoring (if hosted data path).
    Review: SRR (System Requirements Review)
    Exit criteria: Baseline requirements; agreed ICD skeleton; V&V approach; Phase B authorization.

Phase B — Preliminary Design & Technology Completion

Objectives

  • Mature design to preliminary baseline; confirm interfaces with rideshare; freeze critical parts; place long-lead orders.
    Artifacts

  • System/Subsystem Preliminary Design (block diagrams, schematics, models), Preliminary Fault Management / FDIR, Updated ICD (mechanical, electrical, data, EMC), VCRM (Verification Cross-Reference Matrix) v1, Preliminary I&T plan, Configuration Management (CM) Plan, Quality plan & workmanship standards, Safety hazards analysis (PHA/FMEA start), Environmental test plan draft (vibe/acoustic/TVAC/EMI-EMC), Ground segment concept (if deployed), Ops concept & timelines, Long-lead procurement list, Regulatory plan (spectrum, remote sensing).
    Review: PDR (Preliminary Design Review)
    Exit criteria: Preliminary baseline, ICD ≥80% defined, long-lead placed, risks trending down.

Phase C — Final Design & Fabrication

Objectives

  • Complete detailed design; release drawings/firmware/software; fabricate EDU/Protoqual/Flight units; finalize procedures & tests.
    Artifacts

  • CDR package: detailed CAD/Drawings/BOMs; Schematics & board layouts; Thermal/structural/EMC analyses; Software detailed design (requirements traceability); ICD freeze with host; VCRM v2 (with acceptance criteria); I&T Procedures; Environmental Test Procedures; Safety analyses (FMEA/FTA updates); Ops Products (commissioning timelines, contingency procedures).
    Reviews: CDRMRA (Manufacturing Readiness Assessment) for boards/mech as needed.
    Exit criteria: Released design; ICD signed; build authorized.

Phase D — System Assembly, Integration, Test, and Launch

Objectives

  • Build, integrate, verify & validate; complete environmental tests; deliver to integrator; support LV/host integration; launch & checkout.
    Artifacts

  • AIV plan execution; Test Reports (functional, vibe, acoustic, TVAC, EMC), Software qualification reports; As-Built Configuration; Non-conformance & waivers; Logistics & shipping plan; Launch Site procedures; Ground segment readiness.
    Reviews: TRR (Test Readiness), QR/PRR (Qualification/Pre-ship), FRR (Flight Readiness), ORR (Operations Readiness).
    Exit criteria: Flight article delivered & accepted; launch campaign complete; on-orbit checkout successful.

Phase E — Operations & Sustainment

Objectives

  • Nominal ops, data delivery, performance monitoring, anomaly resolution, updates/patches (if allowed), reporting.
    Artifacts

  • Ops handbook, Anomaly response tree & fault rules, KPIs & performance budgets, Data management plan, Calibration/validation plan (if science payload), Monthly/quarterly status & lessons learned.
    Reviews: MOR (Mission Operations Review), periodic ops reviews.

Phase F — Closeout & Disposal

Objectives

  • Execute end-of-life (EOL) passivation/disposing plan per host and regulations; archive data & configuration; finalize lessons learned.
    Artifacts

  • EOL report, Data archive (formats, DOIs as relevant), Final performance assessment, Lessons Learned.


3) Systems Engineering Management (SEMP) Content

3.1 Technical Baseline & Requirements

  • Hierarchy: L1 mission goals → L2 payload system requirements → L3 subsystem specs.

  • Quality of requirements: unique, verifiable, bounded (with margins).

  • Budgets: mass, power (peak/avg), thermal, data rate/volume, pointing/jitter, environments, EMC, reliability.

  • Margins: define by phase (e.g., mass +20% Phase A → +10% Phase C; power +30% → +20%; thermal headroom; link margin ≥3 dB unless justified).

  • ICD: mechanical envelope, keep-out zones, CG/CM, fasteners; electrical (power profile, inrush limits, grounding/bonding, discrete/serial/ethernet links); data (protocols, packet definitions, timing); EMC/EMI limits; thermal interfaces; optical/RF interfaces; handling/cleanliness.

3.2 Architecture & Design

  • Trade studies: COTS vs custom; ADC/DAC precision; SDR vs fixed RF; onboard processing vs ground; harness vs backplane; materials/thermal straps.

  • Reliability & FM: FDIR states, safe-mode entry/exit, watchdogs, brownout/over-current responses, single-event mitigation (TMR, EDAC), redundancy philosophy (cold vs warm).

  • Software & FPGA: standards (coding, reviews, unit/integration tests), requirements traceability, CI builds, static analysis, hardware-in-the-loop (HIL).

3.3 Verification & Validation (V&V)

  • Methods: Test (T), Analysis (A), Inspection (I), Demonstration (D).

  • VCRM: Each requirement mapped to V-method, environment, level (unit/board/subsystem/system), success criteria, witness/sign-off.

  • Qualification approach: Proto-qual (if one-off) vs qual + flight lot.

  • Environments (tailor to LV/host): random vibe, sine burst, acoustic, shock/pyro, TVAC, EMI/EMC (conducted/radiated, susceptibility), deployable tests, burn-in, leak tests, cleanliness.

  • Functional: end-to-end under worst-case power/thermal; latency; data throughput; fault injection; software timing.

3.4 Integration & Test (I&T / AIV)

  • Flow: unit → subsystem → system HIL → environmental → re-test → acceptance.

  • Facilities & EGSE: power supplies with inrush limiting, comms front-ends, data recorders, RF chambers, TVAC chamber, vibe table, clean area.

  • Configuration control: as-designed vs as-built; serialized parts; waiver/deviation board.

  • Readiness gates: TRR entry criteria (procedures released, calibration valid, NCR process active), FRR criteria (all tests closed or dispositioned).

3.5 Safety, Mission Assurance, & Cyber

  • Hazards analyses: PHA → FMEA → FTA; mitigations verified.

  • Workmanship & quality: soldering standards, torque logs, ESD/cleanliness, lot acceptance for EEE parts.

  • Cybersecurity (hosted payloads especially): interface threat model, authentication/command protection, supply-chain controls.

  • Export/ITAR/EAR & site rules baked into integration schedule.

3.6 Project Management

  • WBS & Org: SE, Payload HW, Payload SW/FPGA, AIV, SMA, Ops, Ground, Regulatory, Supply Chain.

  • RACI: see sample below.

  • Schedule logic: pin rideshare ICD freeze and delivery for integration as immovable anchors; set long-lead procurement backward from CDR; hold risk buy-downs before PDR.

  • Cost & reserves: phase-dependent; carry hardware, schedule, and technical reserves; keep management reserve for rideshare slips.

  • Comms & reviews cadence: weekly IPTs; monthly technical/management reviews; risk board biweekly.


4) Rideshare-Specific Planning

  • ICD Lockpoints:

    • T-L ~ CDR-1 month: Mechanical envelope, mounts, CG/CM, mass allocations.

    • T-L ~ CDR: Electrical & data pinouts, power profiles (inrush/peak/average), EMI/EMC limits, grounding.

    • T-L ~ FRR: Final procedures, handling, cleanliness, labeling, shipping & site access.

  • Regulatory/Licensing (as applicable): frequency/spectrum (FCC/NTIA), remote sensing (NOAA), debris assessment & disposal, export licenses for integration country.

  • Host/Deployer Constraints: keep-alive currents, inhibit requirements, battery shipping rules, commanded operations windows, contamination control (optics/RF).

  • Contingency: manifest change, late ICD changes, reduced power/data allocation, integration day anomalies → pre-approved waivers and fallbacks.


5) Budgets & Margins (living documents)

BudgetOwnerv1 DueExit SRRExit PDRExit CDRAcceptance
Mass (incl. fasteners)SE+20%+15%+10%+5%
Power (peak/avg, inrush)EE+30%+25%+20%demo’d
Thermal (hot/cold cases)Thermalworst-caserefinedcorrelatedcorr. to TVAC
Data rate/volume/latencySW/RFlink margin ≥3 dBpacket loss spec’dE2E testedops proven
Pointing/jitter (if needed)GNCreqs setmodelledverifiedon-orbit

(Tailor margins to your center/host standards.)


6) Verification Cross-Reference Matrix (VCRM) — Skeleton

Req IDRequirement (shall)V-MethodLevelEnvironment/ConfigSuccess CriteriaReview Gate
SYS-PWR-001Payload peak power ≤ 35 W for <10 s; avg ≤ 12 WTSystemHot TVAC, max duty cycleMeasured ≤ limitsTRR/FRR
SYS-EMC-010Conducted emissions meet host spec §X.YTSystemEMC chamberWithin limitsTRR
SYS-THERM-020CBE temps within -10…+40 °CA/TSubsys/SystemThermal model + TVACMargins ≥ 5 °CCDR/FRR
SW-LAT-100Cmd→resp latency ≤ 200 msTSystem HILWorst-case load≤ 200 msORR

7) I&T Flow (high level)

  1. Unit functional → 2. Subsystem functional + HIL → 3. System functional

  2. EMI/EMC pre-screen (optional but recommended)

  3. Environmental qual (vibe/acoustic/shock → TVAC → EMC)

  4. Final functional & workmanship inspection

  5. Pre-ship review (PSR)Ship to integrator

  6. Host fit-checkInterface testsFRRLaunch site ops


8) Ground Segment & Operations (Phase E)

  • LEOP/Commissioning plan: timelines, stepwise power-on, RF checks, thermal stabilization, initial data take.

  • Nominal ops: pass plans, autonomy rules, duty cycles vs host allocations, data downlink & processing.

  • Contingencies: comm loss, latch-ups, power brownouts, safe-mode; return-to-service procedures.

  • Performance monitoring: trending of power/thermal/data, alert thresholds.

  • Configuration control in ops: versioned procedures, command loads, patch policy (if applicable).


9) Regulatory, Export, and Safety

  • Spectrum: licensing, frequency coordination, call signs, emissions masks, ITU filings (if applicable via provider).

  • Remote sensing (if imaging): NOAA licensing & data policy.

  • Debris & disposal: match host plan; for deployables, deorbit lifetime & passivation.

  • Export/ITAR/EAR: part lists, integration site licenses, shipping paperwork timeline.

  • Site safety: ESD/cleanliness, batteries/pressurant rules, payload hazards closure.


10) Risk, Opportunity & Issue Management

Likelihood (L) × Consequence (C), 5×5 matrix; risk burn-down reviews biweekly.

IDRiskCauseLCMitigationTriggerOwner
R-01ICD change lateHost redesign34Reserve mass/power; adapter plate; buffer in harness lengthsICD rev > PDR+1SE
R-02EMC failureSwitching noise25Spread-spectrum, filters; pre-screenPre-screen > −6 dB marginEE
R-03Export delayLicense lead time33Early application, alternate site planT-L-120dPM

11) Configuration & Data Management

  • CM: single source of truth (PLM or repo); drawing/BOM release at CDR; as-built EIDPs.

  • Change control: CCB with SE/SMA/PM; deviations/waivers tracked.

  • Data management: test data schemas, calibration files, ops data retention & public release (if applicable).


12) Team, WBS, and RACI (sample)

Core roles: PM, SE, EE, ME, Thermal, RF/Comms, SW/FPGA, AIV Lead, SMA/QA, Regulatory, Ops, Supply Chain.

TaskPMSEEEMESWAIVSMAReg
ConOps/ReqsARCCCCCC
ICD w/ HostCRRRCCCC
BudgetsCRRRRCC
V&V/VCRMCRCCCRC
I&T PlanCRCCCRC
RegulatoryCCR

(R=Responsible, A=Accountable, C=Consulted, –=None)


13) Schedule Backbone

Milestone Backbone

Nov 20, 2025 — PDR. Phase B wrap; ICD v0.8; budgets v1 locked.
Nov 25–Dec 5, 2025 — Long-lead POs. (radiation-tolerant parts, custom PCBs, optics, harness).
Jan 15, 2026 — CDR. Detailed design released; ICD v1.0 for host.
Jan 16–Feb 12, 2026 — Fabrication & assembly (EDU/Flight).
Feb 3–Feb 21, 2026 — Bring-up & unit functional.
Feb 17–Mar 3, 2026 — System integration & HIL.
Feb 24–Feb 27, 2026 — EMI/EMC pre-screen.
Mar 4, 2026 — TRR.
Mar 5–Mar 30, 2026 — Qualification campaign.

  • Vibe/Acoustic/Shock: Mar 5–14

  • TVAC: Mar 16–25

  • EMI/EMC: Mar 26–30
    Mar 31–Apr 5, 2026 — Fixes/retest buffer.
    Apr 6–Apr 9, 2026 — Final functional & acceptance.
    Apr 10, 2026 — PSR (Pre-Ship Review).
    Apr 11, 2026 — Ship to integrator (DDI).
    Apr 15–Apr 22, 2026 — Host fit-check & interface tests.
    Apr 29, 2026 — FRR (Flight Readiness Review).
    May 1–May 10, 2026 — Launch-site procedures & T-0 prep.
    May 12, 2026 — ORR (Operations Readiness Review).
    May 15, 2026 — Commissioning (LEOP) start.

Tracks & owners (what runs in parallel)

  • Systems/Interfaces: Phase-B wrap (now→Nov 14), requirements freeze, ICD v0.8 at PDR; ICD v1.0 at CDR.

  • Regulatory: FCC/NOAA/ITU filings Nov 1, 2025 → Feb 28, 2026 (goal: approvals in hand before TRR).

  • Supply Chain: Long-leads placed by Dec 5; track delivery vs. CDR.

  • Software/FPGA: Requirements at PDR; detailed design at CDR; HIL tests by Mar 3; delivery for TRR.

  • SMA/QA: PHA/FMEA/FTA updated at CDR; workmanship plans active through AIV; NCR/waiver board staffed for March.

  • AIV: Pre-screens in Feb; qual in March; acceptance in April; ship Apr 11.

Reserves & assumptions

  • Schedule reserve: ≥20% on critical path (buffer already shown Mar 31–Apr 5).

  • Logistics: Export licenses & site access included in Regulatory track; dry-run shipping docs by Mar 20.

  • Rideshare anchors: ICD freeze at CDR, DDI Apr 11, FRR Apr 29. Launch date itself is provider-controlled.


14) Deliverables Checklist by Review

SRR: ConOps, SRD, ICD v0.5, SEMP, Budgets v1, V&V strategy, Risk Log v1, SMA plan, Software plan, Regulatory plan.
PDR: Preliminary design package, ICD v0.8, VCRM v1, I&T plan draft, Environmental plan draft, FMEA/PHA, Long-lead list, Updated budgets, Config & QA plans.
CDR: Released drawings/BOMs, Software detailed design, ICD v1.0 (signed), Test procedures, VCRM v2 with acceptance criteria, Safety updates, Manufacturing plans.
TRR: Test procedures approved, calibrated EGSE, configs frozen, hazards closed to test.
FRR/PSR: All test reports with closures, NCRs dispositioned, as-built EIDP, shipping plan, site procedures, operations handbook draft.
ORR: Commissioning procedures, anomaly rules, ground readiness, data pipeline validated.


15) Immediate Next Actions (you can start these today)

  1. Draft one-page ConOps (user goals, timelines, operating modes).

  2. Start ICD assumption sheet from host/deployer datasheets (envelope, power, data, EMC).

  3. Stand up risk log and budget workbook (mass/power/thermal/data).

  4. Create SEMP v0.1: org/RACI, review calendar, V&V philosophy, CM & QA, regulatory path.

  5. Identify long-leads (radiation-tolerant parts, precision optics, custom PCBs, HV supplies).

  6. Put hard anchors on the schedule: ICD freeze date, DDI (delivery), FRR window.