By end-of-day Nov 3 - Plan, create/update test scripts in ALM. (SAP Business Areas)
End of day production snapshot from 9/18/2023 to be used to refresh SF3 environment
End of day production snapshot from 9/26/2023 to be used to refresh SH1 environment
End of day production snapshot from 10/16/2023 to be used to refresh SH2 environment

Refer to calendar for detailed time frames

2023 SAP Support Pack Upgrade - Calendar View

Oct 5: SAP releases year-end support pack versions
Oct 13-18: SF3 upgrade
Oct 16:  SH1 ready for use
Oct 20 at 5PM: start of SF2 restricted window
Oct 21-24: SF2 upgrade
Oct 24 at 5PM: start of SH2 restricted window
Oct 25-Oct 31: SH2 refresh and upgrade
Nov 2-3: IS&T Controlled Payroll Test
Nov 6-28: SH2 business testing
Nov 29 -Dec 1 - Uptime Production Cut-over Activities -
Dec 1-Dec 3 - Go-live weekend! (start Friday at 5pm)
Dec 4 - Upgraded  PS1 is ready for use


---------


SAP Scheduled Upgrades - Ancillary Systems

ERP (systems SF3, SF2, SH2, PS1):

-- EHP8 for SAP ERP 6.0 SPS 21 with HR SP 0124 (a.k.a. C4)

---- SAP KERNEL 7.54 64-BIT UNICODE PL 200

---- SMERP  630_740  SP 0012

---- SMFND  630_740  SP 0012

 

NetWeaver ADS (systems DSD, DST, DSP):

-- NetWeaver 750 SPS 28 with SAP JVM 8.1.095 (or higher)

 

NetWeaver/GRC (systems ACD, ACT, ACP):

---- SAP KERNEL 7.54 64-BIT UNICODE PL 200

---- NetWeaver 7.52 SPS 13 (estimated to be available by October 16th)

---- GRC Access Control 12.0 SPS 22

 

SAP Business Technology Platform (formerly SCP) HANA DB:

-- HANA 2.00.059.09 or higher

 

SAP Mobile:   N/A for 2023

 

 

 




 