This folder contains current copies of relevant project schedules.  These schedules are attached in MSProject format an presented in HTML format.

High Level Plan for SAPBiz 10-8-08 v4 (last updated 14 Oct 2008)

Project Start Date: Sat 9/20/08
Project Finish Date: Tue 12/23/08

Task_Data

ID

Task_Name

Duration

Start_Date

Finish_Date

Predecessors

Resource_Names

1

2008 Support Pack Implementation Project

65 days

Mon 9/22/08

Tue 12/23/08

 

 

2

Project Prep

33 days

Mon 9/22/08

Thu 11/6/08

 

 

3

PS1 Snapshot at end of day

0 days

Mon 9/22/08

Mon 9/22/08

 

 

4

Transaction list available

0 days

Fri 9/26/08

Fri 9/26/08

 

R3

5

Identify test scenarios / transactions

5 days

Mon 9/29/08

Fri 10/3/08

4

BUS,BA

6

Review and update test scripts

20 days

Mon 10/6/08

Fri 10/31/08

5

BUS,BA

7

SF3 Unavailable at end of day

0 days

Fri 10/10/08

Fri 10/10/08

 

 

8

PS1 snapshot at end of day

0 days

Mon 10/20/08

Mon 10/20/08

 

R3

9

Execute Trial balance for snapshot

0.5 days

Mon 10/20/08

Mon 10/20/08

8

BUS

10

Save data warehouse extracts

0 days

Fri 10/10/08

Fri 10/10/08

7

DWH

11

Support packs available from SAP

0 days

Mon 10/20/08

Mon 10/20/08

 

 

12

PS1 Import 1

0 days

Thu 10/23/08

Thu 10/23/08

 

 

13

PS1 Import 2

0 days

Thu 10/30/08

Thu 10/30/08

 

 

14

PS1 Import 3

0 days

Thu 11/6/08

Thu 11/6/08

 

 

15

SF3 System Refresh

5 days

Tue 10/14/08

Mon 10/20/08

 

 

16

Refresh with 9/22/08 PS1 Snapshot

2 days

Tue 10/14/08

Wed 10/15/08

 

R3

17

R3 Action Log

0.5 days

Thu 10/16/08

Thu 10/16/08

16

R3

18

Scramble sensitive data

2.5 days

Thu 10/16/08

Mon 10/20/08

17

R3

19

PS1 Snapshot at end of day

0 days

Mon 10/20/08

Mon 10/20/08

 

 

20

Execute Trial Balance for later comparison

0.5 days

Mon 10/20/08

Mon 10/20/08

19

R3

21

Support Packs available from SAP

0 days

Mon 10/20/08

Mon 10/20/08

 

 

22

SFK Update

4 days

Tue 10/21/08

Fri 10/24/08

 

 

23

Import Updates

1 day

Tue 10/21/08

Tue 10/21/08

21FS+1 day

R3

24

Identify and resolve import issues

1 day

Wed 10/22/08

Wed 10/22/08

23

R3

25

Validate security infrastructure (SNC)

1 day

Thu 10/23/08

Thu 10/23/08

24

R3

26

Validate SAPGui interactions

0.5 days

Fri 10/24/08

Fri 10/24/08

25

R3

27

Validate basic SAP functions work

0.5 days

Fri 10/24/08

Fri 10/24/08

26

R3

28

SF3 Update

5 days

Mon 10/27/08

Fri 10/31/08

 

 

29

Import Updates

2 days

Mon 10/27/08

Tue 10/28/08

21,27

R3

30

Execute action log

0.5 days

Wed 10/29/08

Wed 10/29/08

29

DEV,BA

31

Update action log as necessary

0.5 days

Wed 10/29/08

Wed 10/29/08

 

DEV,BA

32

Produce collision report

0.5 days

Wed 10/29/08

Wed 10/29/08

29

R3

33

Review collision report

1 day

Wed 10/29/08

Thu 10/30/08

32

DEV,BA

34

Reimplement MIT mods

1 day

Thu 10/30/08

Fri 10/31/08

33

DEV

35

Confirm configuration steps work

0.5 days

Fri 10/31/08

Fri 10/31/08

34

DEV,BA

36

Unit Test Preparation and Execution

6 days

Mon 11/3/08

Mon 11/10/08

 

 

37

Apply support packs to SF2

2 days

Mon 11/3/08

Tue 11/4/08

35

R3

38

Update and Execute action log

0.5 days

Wed 11/5/08

Wed 11/5/08

37

BA,DEV

39

Import transports from SF3

0.5 days

Wed 11/5/08

Wed 11/5/08

38

R3

40

Unit test, resolution and retest in SF2

3 days

Thu 11/6/08

Mon 11/10/08

39

BA,DEV

41

System Test / User Acceptance Test Environment Preparations

10 days

Mon 10/27/08

Fri 11/7/08

 

 

42

Refresh TST with 10/20 snapshot, NO SCRAMBLING DATA

3 days

Mon 10/27/08

Wed 10/29/08

 

R3

43

Import post snapshot production transports (delta from 10/20 to 10/30)

2 days

Thu 10/30/08

Fri 10/31/08

42

R3

44

Import updates

2 days

Mon 11/3/08

Tue 11/4/08

43

R3

45

Import SF3 transports & post-update DEV transports (to be tested during SI & UAT)

1 day

Wed 11/5/08

Wed 11/5/08

44

DEV

46

Execute trial balance and compare with TB from 10/20

0.5 days

Thu 11/6/08

Thu 11/6/08

44,45

BUS

47

Execute action log

0.5 days

Thu 11/6/08

Thu 11/6/08

46

DEV,BA

48

Execute DWH extracts and comparison

1 day

Fri 11/7/08

Fri 11/7/08

47

DWH

49

Development slowdown starts

0 days

Fri 11/7/08

Fri 11/7/08

48

 

50

Execute System Integration Tests

6 days

Wed 11/12/08

Wed 11/19/08

 

 

51

HR-Payroll

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

52

Logistics

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

53

EHS

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

54

Financial

6 days

Wed 11/12/08

Wed 11/19/08

47,40

DEV,BA

55

Execute User Acceptance Test (UAT)

15 days

Thu 11/20/08

Fri 12/12/08

 

 

56

Payroll comparison (tasks and duration to be validated)

3 days

Thu 11/20/08

Mon 11/24/08

54

BA,BUS

57

Execute UAT

7 days

Tue 11/25/08

Fri 12/5/08

56

BUS

58

Financial Close

1 day

Mon 12/8/08

Mon 12/8/08

57

BUS

59

Issue retesting

2 days

Tue 12/9/08

Wed 12/10/08

58

ALL

60

Execute another financial close?

1 day

Thu 12/11/08

Thu 12/11/08

59

BUS

61

UAT sign off

1 day

Fri 12/12/08

Fri 12/12/08

60

ALL

62

Cutover weekend & Controlled Start

2 days

Sat 12/13/08

Sun 12/14/08

61

ALL

63

Drop Dead Date for support packs in production

0 days

Mon 12/22/08

Mon 12/22/08

 

 

64

First Calendar 2009 Payroll

0 days

Tue 12/23/08

Tue 12/23/08

 

 