High-Level Timeline
Now - October - Plan, convert/create/update test scripts in QC, move pending support & project work into production
10/11/2012 – SAP release of year end base level support pack
10/20-21/2012 – Production outage; DB & OS upgrade
Day |
Start |
End |
Task |
Area Responsible |
10/20 Saturday |
1:30am |
7:00am |
System Backups |
OIS |
10/20 Saturday |
7:00am |
11:00am |
Oracle Upgrade |
R3-Admin |
10/20 Saturday |
7:00am |
10/21 Sunday 1:00am |
Linux System Upgrade |
OIS |
10/21 Sunday |
1:00am |
8:00am |
Post Linux Upgrade SAP Processing |
R3-Admin |
10/21 Sunday |
8:00am |
9:00am |
Production Validation |
Admin Systems, Tech Services |
10/21 Sunday |
9:00am |
|
System Opened up to the MIT Community |
R3-Admin |
10/22/2012 - End of day production snapshot to be used to refresh test environments
10/22/2012 - Development Freeze begins
11/01/2012 - Last date to implement support & enhancement changes until freeze ends on 12/5/2012
10/26/2012 - 11/2/2012 Unit test
11/5/2012 - 11/27/2012 System Integration Test
12/1/2012 - 12/2/2012 Go-live weekend!
12/5/2012 - Development Freeze ends