High-Level Timeline (**proposed**)


(info) September thru the end of October - Plan, convert/create/update test scripts in ALM, move pending support & project work into production
(blue star) 10/12/2017 - SAP release of year end base level support pack
(info) 10/13/2017 - Last date to implement support & enhancement changes until freeze ends on 12/07/2017
(info) 10/16/2017 - Development Freeze begins
(info) 10/16/2017 - End of day production snapshot to be used to refresh test environments (9/18 for SF3)
(info) 10/23/2017 - Unit test

(info) 10/30/2017 - 10/31/2017 Controlled Payroll Runs (SH2)

(info) 11/01/2017 - System Integration Test (regression test fixes: 11/21-22/2017)

(warning) 12/01/2017 - Go-live weekend!

(info) 12/06/2017 - Development Freeze ends