High-Level Timeline
Now (July) thru the end of October - Plan, convert/create/update test scripts in ALM/QC, move pending support & project work into production
10/08/2015 - SAP release of year end base level support pack
10/19/2015 - End of day production snapshot to be used to refresh test environments
10/19/2015 - Development Freeze begins
10/22/2015 - Last date to implement support & enhancement changes until freeze ends on 12/16/2015
10/23/2015 - Unit test
11/02/2015 - System Integration Test (regression test fixes: 11/24-25/2015)
12/11/2015 - Go-live weekend!
12/16/2015 - Development Freeze ends