High-Level Timeline


 

(info) Now (July) thru the end of October - Plan, convert/create/update test scripts in ALM/QC, move pending support & project work into production
(info) 10/08/2015 - SAP release of year end base level support pack
(info) 10/19/2015 - End of day production snapshot to be used to refresh test environments
(info) 10/19/2015 - Development Freeze begins
(info) 10/22/2015 - Last date to implement support & enhancement changes until freeze ends on 12/16/2015
(info) 10/23/2015 - Unit test

(info) 11/02/2015 - System Integration Test (regression test fixes: 11/24-25/2015)

(info) 12/11/2015 - Go-live weekend!

(info) 12/16/2015 - Development Freeze ends

(big grin)


File Size Creator Created Comment

Copy of SoH_MIT_Timeline v3.xlsx

27447

[~snc@mit.edu]

Jun 25, 2015 11:32  

MIT HANA Migration Schedule 20150715 V005.mpp

403456

[~snc@mit.edu]

Jul 15, 2015 10:17  

 

 

 

  • No labels