UHF Amplifier Project Plan
General Plan
Learn to use the tools (Wiki, Gensys, Altium Protel)
Design Specification
Design overall System Architecture based on specification
System Level Design review
Breakup overall system Design into sub system
Decide which sub system to design first, second etc.
Consider major components necessary for each sub system, Order Parts
Detailed sub system design with a initial layout, Order Parts
Design review
Combine layouts on final PCB, Order PCB
Assemble Initial PCB while remainder are assembled
Test Initial PCB including debugging
Test and Assemble remaining PCB boards
Test Final Amplifier including debugging
Project Rules
The project will be documented in the Millstone Hill Science wiki.
Hardware schematics will be properly annotated.
Hardware schematics will be accompanied with a parts list. This will be necessary for professional assembly.
All test results will be documented in the Millstone Hill Science wiki
Work smarter, not harder.
Approximate Timeline
June 2, 2008 : Students Arrive
week ending June 6, 2008 : Initial Orientation, Reading and Learning Software Tools
week ending June 13, 2008 : Testing of AMISR Amplifier, Learning Software Tools, Preliminary Design
week of June 15-20, 2008 : CEDAR meeting
week ending June 27, 2008 : Electrical and Thermal Design,
week ending July 3, 2008 : Finalize Design, Layout, Order Parts
week ending July 11, 2008 : Layout, Order PCB(s),Assemble Initial Board
week ending July 18, 2008 : Test Initial Board(s. Send out boards for assembly
week ending July 25, 2008 : Assembly of Final Amplifier
week ending August 1, 2008 : Testing of Final Amplifier,(presentation/demo practice)
week ending August 8, 2008 : REU Presentations