Now - October - Plan, convert/create/update test scripts in QC, move pending support & project work into production

10/13/2011 – SAP release of year end base level support pack

10/17/2011 - End of day production snapshot to be used to refresh test environments

10/24/2011 - Development Freeze begins

11/01/2011 - Last date to implement support & enhancement changes until freeze ends on 12/7/2011

10/28/2011 - 11/4/2011 Unit test

11/7/2011 - 11/28/2011 System Integration Test

12/2/2011 - 12/4/2011 Go-live weekend!

12/7/2011 - Development Freeze ends