High-Level Timeline
By end-of-day Oct 31 - Plan, create/update test scripts in ALM. (SAP Business Areas)
End of day production snapshot from 9/21/2026 to be used to refresh SF3 environment
End of day production snapshot from 9/21/2026 to be used to refresh SH1 environment
End of day production snapshot from 10/19/2026 to be used to refresh SH2 environment
Refer to calendar for detailed time frames
2026 SAP Support Pack Upgrade - Calendar View
Oct 8: SAP releases year-end support pack versions
Oct 12-16: SF3 upgrade
Oct 19: SH1 ready for use
Oct 20 at 5PM: start of SF2 restricted window
Oct 19-22: SF2 upgrade
Oct 19 at 5PM: start of SH2 restricted window
Oct 21-Oct 27: SH2 refresh and upgrade
Oct 29 - Oct 30: IS&T Controlled Payroll Test
Nov 2-24: SH2 business testing
Dec 2 - 4 - Uptime Production Cut-over Activities -
Dec 4 -Dec 6 - Go-live weekend! (start Friday at 5pm)
Dec 7 - Upgraded PS1 is ready for use
---------